Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
114
matching recommendationsSIC | 29 | Petroleum And Coal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0604 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,064 | $0 | Implemented |
SD0604 # 04 Y:2020 | 04 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,562 | $3,960 | Implemented |
SD0604 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,750 | $1,200 | Implemented |
SF0545 # 03 Y:2019 | 03 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,924 | $11,386 | Implemented |
SF0545 # 01 Y:2019 | 01 | 2019 | INSULATE BARE EQUIPMENT | $1,151 | $1,194 | Implemented |
SF0545 # 06 Y:2019 | 06 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $238,757 | $1,300,334 | Implemented |
SF0505 # 08 Y:2017 | 08 | 2017 | INSULATE BARE EQUIPMENT | $1,069 | $1,882 | Implemented |
SF0505 # 07 Y:2017 | 07 | 2017 | INSULATE BARE EQUIPMENT | $3,828 | $5,423 | Implemented |
SF0433 # 01 Y:2013 | 01 | 2013 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,312 | $393 | Implemented |
SF0433 # 02 Y:2013 | 02 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,790 | $3,152 | Implemented |
SF0433 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $7,030 | $21,402 | Implemented |
SF0433 # 06 Y:2013 | 06 | 2013 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $9,806 | $46,860 | Implemented |
SD0453 # 01 Y:2012 | 01 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $19,250 | $200 | Implemented |
SD0453 # 02 Y:2012 | 02 | 2012 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,500 | $200 | Implemented |
SD0453 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,950 | $200 | Implemented |
SD0453 # 04 Y:2012 | 04 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,913 | $2,000 | Implemented |
SD0453 # 05 Y:2012 | 05 | 2012 | INSULATE BARE EQUIPMENT | $49,200 | $24,400 | Implemented |
SD0453 # 07 Y:2012 | 07 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,700 | $12,150 | Implemented |
SF0387 # 08 Y:2010 | 08 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,393 | $2,851 | Implemented |
SF0387 # 10 Y:2010 | 10 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,160 | $3,840 | Implemented |
SF0387 # 06 Y:2010 | 06 | 2010 | USE OPTIMUM THICKNESS INSULATION | $791 | $1,536 | Implemented |
SF0387 # 05 Y:2010 | 05 | 2010 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,964 | $7,727 | Implemented |
SF0387 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,874 | $1,627 | Implemented |
SF0387 # 11 Y:2010 | 11 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,342 | $6,259 | Implemented |
SF0387 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $747 | $0 | Implemented |