IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

115

matching recommendations
Reset
SIC 308 Miscellaneous Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0585 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,028 $2,305 Implemented
OR0585 # 03 Y:2012 03 2012 INSTALL TIMERS AND/OR THERMOSTATS $1,776 $500 Not Implemented
OR0585 # 02 Y:2012 02 2012 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,690 $2,000 Not Implemented
OR0585 # 01 Y:2012 01 2012 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $8,836 $7,417 Not Implemented
OR0460 # 02 Y:2004 02 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $5,070 $1,830 Implemented
OR0460 # 04 Y:2004 04 2004 INSTALL EQUIPMENT TO MOVE PRODUCT $37,500 $14,200 Not Implemented
OR0460 # 03 Y:2004 03 2004 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $16,000 $0 Implemented
OR0460 # 01 Y:2004 01 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,300 $1,500 Implemented
OR0460 # 05 Y:2004 05 2004 MOVE PRODUCT USING MECHANICAL MEANS $7,850 $2,320 Implemented
OR0336 # 04 Y:1999 04 1999 OPTIMIZE PLANT POWER FACTOR $3,716 $10,200 Not Implemented
OR0336 # 03 Y:1999 03 1999 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION $27,050 $8,200 Not Implemented
OR0336 # 02 Y:1999 02 1999 INSTALL SENSORS TO DETECT DEFECTS $31,700 $0 Implemented
OR0336 # 01 Y:1999 01 1999 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $93,600 $200,000 Implemented
OR0337 # 05 Y:1999 05 1999 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES $11,000 $28,700 Implemented
OR0337 # 04 Y:1999 04 1999 USE LESS WASTEFUL PACKAGING $34,000 $73,000 Not Implemented
OR0337 # 03 Y:1999 03 1999 INSULATE BARE EQUIPMENT $9,949 $13,663 Implemented
OR0337 # 02 Y:1999 02 1999 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $2,060 $0 Implemented
OR0337 # 01 Y:1999 01 1999 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $44,432 $21,400 Not Implemented
OR0324 # 02 Y:1998 02 1998 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $88,020 $60,000 Not Implemented
OR0324 # 06 Y:1998 06 1998 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,935 $2,000 Implemented
OR0324 # 03 Y:1998 03 1998 REDUCE SCRAP PRODUCTION $34,430 $11,000 Not Implemented
OR0324 # 04 Y:1998 04 1998 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $11,110 $42,200 Not Implemented
OR0324 # 05 Y:1998 05 1998 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $5,950 $800 Not Implemented
OR0324 # 07 Y:1998 07 1998 RECOVER WASTE HEAT FROM EQUIPMENT $3,860 $3,700 Implemented
OR0324 # 08 Y:1998 08 1998 INSTALL / REPAIR INSULATION ON STEAM LINES $2,460 $1,060 Implemented