Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
383
matching recommendationsSIC | 3231 | Products Of Purchased Glass |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0433 # 05 Y:2002 | 05 | 2002 | INSTALL OCCUPANCY SENSORS | $1,228 | $4,000 | Implemented |
WI0433 # 06 Y:2002 | 06 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $519 | $740 | Implemented |
OR0417 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,232 | $0 | Implemented |
OR0417 # 03 Y:2002 | 03 | 2002 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $6,232 | $900 | Implemented |
OR0417 # 05 Y:2002 | 05 | 2002 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,731 | $1,800 | Implemented |
OR0417 # 06 Y:2002 | 06 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,389 | $26,990 | Implemented |
UD0614 # 02 Y:2001 | 02 | 2001 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $53,184 | $30,570 | Implemented |
UD0614 # 05 Y:2001 | 05 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,252 | $0 | Implemented |
NC0185 # 01 Y:2000 | 01 | 2000 | ADJUST BURNERS FOR EFFICIENT OPERATION | $637 | $800 | Implemented |
NC0185 # 03 Y:2000 | 03 | 2000 | DISCONNECT BALLASTS | $441 | $500 | Implemented |
NC0185 # 05 Y:2000 | 05 | 2000 | USE OPTIMUM THICKNESS INSULATION | $4,274 | $1,200 | Implemented |
NC0185 # 06 Y:2000 | 06 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,584 | $50 | Implemented |
NC0185 # 08 Y:2000 | 08 | 2000 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $4,750 | $1,000 | Implemented |
CO0460 # 01 Y:2000 | 01 | 2000 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,940 | $7,500 | Implemented |
CO0460 # 04 Y:2000 | 04 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $430 | $670 | Implemented |
CO0460 # 05 Y:2000 | 05 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $240 | $600 | Implemented |
CO0460 # 06 Y:2000 | 06 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $200 | $210 | Implemented |
CO0460 # 08 Y:2000 | 08 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $166,400 | $40,000 | Implemented |
CO0460 # 09 Y:2000 | 09 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $72,730 | $122,000 | Implemented |
UF0243 # 01 Y:2000 | 01 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,393 | $0 | Implemented |
UF0243 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,494 | $0 | Implemented |
UF0243 # 04 Y:2000 | 04 | 2000 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $24,816 | $0 | Implemented |
UF0243 # 05 Y:2000 | 05 | 2000 | OPTIMIZE PLANT POWER FACTOR | $2,493 | $0 | Implemented |
UF0243 # 06 Y:2000 | 06 | 2000 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $17,680 | $0 | Implemented |
UF0239 # 02 Y:1999 | 02 | 1999 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,096 | $0 | Implemented |