Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
115
matching recommendationsSIC | 339 | Miscellaneous Primary Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0217 # 06 Y:2002 | 06 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $300 | $50 | Not Implemented |
UM0217 # 07 Y:2002 | 07 | 2002 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $2,860 | $2,500 | Implemented |
UM0217 # 08 Y:2002 | 08 | 2002 | ADJUST BURNERS FOR EFFICIENT OPERATION | $2,050 | $1,350 | Implemented |
UM0217 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $396 | $75 | Implemented |
UM0217 # 02 Y:2002 | 02 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $310 | $600 | Implemented |
UM0213 # 05 Y:2002 | 05 | 2002 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $11,201 | $500 | Implemented |
UM0213 # 06 Y:2002 | 06 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,292 | $3,000 | Implemented |
UM0213 # 01 Y:2002 | 01 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $40,905 | $1,000 | Not Implemented |
UM0213 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,927 | $71,714 | Implemented |
UM0213 # 03 Y:2002 | 03 | 2002 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $23,514 | $500 | Implemented |
UM0213 # 04 Y:2002 | 04 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $22,460 | $3,600 | Implemented |
UM0213 # 07 Y:2002 | 07 | 2002 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,355 | $1,468 | Implemented |
UM0181 # 01 Y:2001 | 01 | 2001 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $300 | $300 | Not Implemented |
UM0181 # 02 Y:2001 | 02 | 2001 | USE OPTIMUM THICKNESS INSULATION | $3,470 | $3,540 | Not Implemented |
UM0181 # 03 Y:2001 | 03 | 2001 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $94,100 | $71,000 | Not Implemented |
UM0181 # 04 Y:2001 | 04 | 2001 | IMPROVE SPACE COMFORT CONDITIONING | $4,520 | $8,000 | Not Implemented |
UM0176 # 05 Y:2000 | 05 | 2000 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $51,717 | $8,050 | Not Implemented |
UM0176 # 04 Y:2000 | 04 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $127,531 | $162,750 | Not Implemented |
UM0176 # 06 Y:2000 | 06 | 2000 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $425,187 | $800,000 | Not Implemented |
UM0176 # 01 Y:2000 | 01 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $733 | $500 | Not Implemented |
UM0176 # 03 Y:2000 | 03 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,038 | $2,201 | Not Implemented |
UM0176 # 02 Y:2000 | 02 | 2000 | INCREASE AMOUNT OF CONDENSATE RETURNED | $72,582 | $15,000 | Not Implemented |
UM0162 # 02 Y:2000 | 02 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $15,362 | $10,000 | Implemented |
UM0162 # 03 Y:2000 | 03 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,628 | $10,800 | Implemented |
UM0162 # 04 Y:2000 | 04 | 2000 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $15,894 | $12,000 | Implemented |