IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

853

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0597 # 01 Y:2000 01 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,212 $19,769 Implemented
OK0597 # 02 Y:2000 02 2000 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $794 $176 Not Implemented
OK0597 # 03 Y:2000 03 2000 OPTIMIZE PLANT POWER FACTOR $2,790 $1,500 Not Implemented
OK0597 # 04 Y:2000 04 2000 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $2,995 $4,000 Not Implemented
OK0597 # 05 Y:2000 05 2000 $19,012 $2,700 Not Implemented
OK0595 # 01 Y:2000 01 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $621 $1,212 Not Implemented
OK0595 # 02 Y:2000 02 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $520 $708 Not Implemented
OK0595 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $19,857 $90,984 Implemented
OK0595 # 04 Y:2000 04 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,695 $3,700 Implemented
OK0595 # 05 Y:2000 05 2000 INSTALL OCCUPANCY SENSORS $664 $2,106 Not Implemented
OK0595 # 06 Y:2000 06 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,855 $6,930 Implemented
OK0595 # 07 Y:2000 07 2000 INCREASE USE OF AUTOMATION $367,920 $150,000 Implemented
OK0595 # 08 Y:2000 08 2000 $227,760 $30,000 Not Implemented
OK0595 # 09 Y:2000 09 2000 $36,400 $65,450 Not Implemented
OK0590 # 01 Y:2000 01 2000 $17,680 $250 Not Implemented
OK0590 # 02 Y:2000 02 2000 $5,824 $3,443 Not Implemented
OK0590 # 03 Y:2000 03 2000 BURN WASTE OIL FOR HEAT $2,892 $3,490 Implemented
OK0590 # 04 Y:2000 04 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,604 $5,081 Not Implemented
OK0590 # 05 Y:2000 05 2000 RECOVER WASTE HEAT FROM EQUIPMENT $2,743 $1,613 Implemented
OK0590 # 06 Y:2000 06 2000 INSTALL OCCUPANCY SENSORS $761 $1,440 Not Implemented
OK0586 # 01 Y:1999 01 1999 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $8,100 $7,000 Not Implemented
OK0586 # 02 Y:1999 02 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,117 $6,500 Implemented
OK0586 # 03 Y:1999 03 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,681 $1,000 Implemented
OK0586 # 04 Y:1999 04 1999 USE PRECIPITATING AGENTS IN WASTE WATER TREATMENT THAT PRODUCE THE LEAST QUANTITY OF WASTE $14,440 $30,000 Implemented
OK0586 # 05 Y:1999 05 1999 $81,900 $50,000 Not Implemented