IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

138

matching recommendations
Reset
SIC 344 Fabricated Structural Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0271 # 11 Y:2001 11 2001 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $100,000 $100,000 Not Implemented
IA0271 # 12 Y:2001 12 2001 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $1,550 $3,400 Implemented
IA0236 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,665 $16,153 Not Implemented
IA0236 # 02 Y:1999 02 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,409 $1,248 Not Implemented
IA0236 # 03 Y:1999 03 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,131 $394 Not Implemented
IA0236 # 04 Y:1999 04 1999 INSTALL OCCUPANCY SENSORS $455 $200 Not Implemented
IA0236 # 05 Y:1999 05 1999 RECYCLE CLEANING SOLVENT AND REUSE $8,966 $7,853 Not Implemented
IA0218 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,310 $14,754 Not Implemented
IA0218 # 02 Y:1999 02 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,756 $20,756 Not Implemented
IA0218 # 03 Y:1999 03 1999 INSTALL OCCUPANCY SENSORS $2,081 $2,195 Not Implemented
IA0218 # 04 Y:1999 04 1999 RECOVER WASTE HEAT FROM EQUIPMENT $876 $87 Not Implemented
IA0218 # 05 Y:1999 05 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $151 $0 Not Implemented
IA0218 # 06 Y:1999 06 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $420 $272 Implemented
IA0218 # 07 Y:1999 07 1999 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT $3,187 $2,656 Not Implemented
IA0172 # 01 Y:1997 01 1997 INSTALL AUTOMATIC PACKING EQUIPMENT $120,000 $150,000 Not Implemented
IA0172 # 02 Y:1997 02 1997 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $90,720 $10,000 Implemented
IA0172 # 03 Y:1997 03 1997 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,126 $17,669 Implemented
IA0172 # 04 Y:1997 04 1997 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $2,906 $7,400 Not Implemented
IA0172 # 05 Y:1997 05 1997 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,649 $743 Implemented
IA0172 # 06 Y:1997 06 1997 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $2,326 $10,347 Implemented
IA0172 # 07 Y:1997 07 1997 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $654 $162 Implemented
IA0172 # 08 Y:1997 08 1997 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $162 $200 Implemented
IA0163 # 01 Y:1997 01 1997 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $1,000,711 $120,000 Not Implemented
IA0163 # 02 Y:1997 02 1997 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $186,892 $520,000 Not Implemented
IA0163 # 03 Y:1997 03 1997 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $56,975 $1,550 Implemented