Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

419

matching recommendations
Reset
SIC 3442 Metal Doors, Sash, And Trim
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MI0431 # 07 Y:2023 07 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $816 $1,400 Implemented
MI0431 # 03 Y:2023 03 2023 OPTIMIZE PLANT POWER FACTOR $8,963 $16,003 Implemented
MI0431 # 06 Y:2023 06 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $5,030 $80 Implemented
MI0431 # 05 Y:2023 05 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,269 $1,020 Implemented
MI0431 # 04 Y:2023 04 2023 INSTALL OCCUPANCY SENSORS $8,323 $680 Implemented
NL0070 # 03 Y:2022 03 2022 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $26,148 $35 Implemented
NL0070 # 06 Y:2022 06 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,590 $23,500 Implemented
NL0070 # 02 Y:2022 02 2022 UPGRADE CONTROLS ON COMPRESSORS $32,832 $16,500 Implemented
NL0070 # 08 Y:2022 08 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $490 $854 Implemented
NL0070 # 07 Y:2022 07 2022 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $675 $3,315 Implemented
TT0280 # 02 Y:2022 02 2022 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING $29,003 $9,880 Implemented
TT0280 # 04 Y:2022 04 2022 TURN OFF EQUIPMENT WHEN NOT IN USE $21,150 $0 Implemented
TT0280 # 05 Y:2022 05 2022 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $19,766 $0 Implemented
TT0280 # 01 Y:2022 01 2022 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $52,932 $4,800 Implemented
TT0274 # 04 Y:2022 04 2022 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,530 $0 Implemented
TT0274 # 02 Y:2022 02 2022 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $4,579 $18,000 Implemented
IP0148 # 05 Y:2021 05 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $125 $522 Implemented
IP0148 # 02 Y:2021 02 2021 TURN OFF EQUIPMENT WHEN NOT IN USE $844 $0 Implemented
IP0148 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,097 $185 Implemented
MZ0301 # 10 Y:2020 10 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,307 $4,100 Implemented
MZ0301 # 07 Y:2020 07 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $604 $200 Implemented
MZ0301 # 08 Y:2020 08 2020 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $304 $52 Implemented
MZ0301 # 03 Y:2020 03 2020 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,820 $7,000 Implemented
MZ0301 # 02 Y:2020 02 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,114 $4,500 Implemented
MZ0301 # 06 Y:2020 06 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,087 $5,000 Implemented