Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,093
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0504 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,551 | $47,880 | Implemented |
WI0504 # 04 Y:2006 | 04 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $5,466 | $1,840 | Implemented |
WI0504 # 06 Y:2006 | 06 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,907 | $1,280 | Implemented |
WI0504 # 07 Y:2006 | 07 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $157 | $0 | Implemented |
LL0240 # 01 Y:2006 | 01 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $40,093 | $2,862 | Implemented |
LL0240 # 02 Y:2006 | 02 | 2006 | USE PHOTOCELL CONTROLS | $28,394 | $1,110 | Implemented |
LL0240 # 03 Y:2006 | 03 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $24,138 | $143,240 | Implemented |
LL0240 # 04 Y:2006 | 04 | 2006 | INSTALL TIMERS AND/OR THERMOSTATS | $15,054 | $726 | Implemented |
LL0240 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,827 | $12,200 | Implemented |
LL0240 # 06 Y:2006 | 06 | 2006 | INSTALL OCCUPANCY SENSORS | $2,004 | $990 | Implemented |
LL0240 # 07 Y:2006 | 07 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,657 | $1,050 | Implemented |
LL0240 # 09 Y:2006 | 09 | 2006 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $21,764 | $230 | Implemented |
UM0293 # 01 Y:2005 | 01 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,861 | $18,165 | Implemented |
UM0293 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,506 | $175 | Implemented |
UM0293 # 03 Y:2005 | 03 | 2005 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,085 | $50 | Implemented |
UM0293 # 06 Y:2005 | 06 | 2005 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $227 | $200 | Implemented |
AS0410 # 03 Y:2005 | 03 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,623 | $100 | Implemented |
AS0410 # 04 Y:2005 | 04 | 2005 | USE PHOTOCELL CONTROLS | $0 | $5,538 | Implemented |
AS0410 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,056 | $1,000 | Implemented |
UM0291 # 01 Y:2005 | 01 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $20,293 | $9,000 | Implemented |
UM0291 # 03 Y:2005 | 03 | 2005 | COVER OPEN TANKS | $4,518 | $2,366 | Implemented |
UM0291 # 04 Y:2005 | 04 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,427 | $1,900 | Implemented |
UM0291 # 07 Y:2005 | 07 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,325 | $1,265 | Implemented |
SD0372 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,173 | $140 | Implemented |
SD0372 # 08 Y:2005 | 08 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,723 | $16,563 | Implemented |