Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,293
matching recommendationsSIC | 353 | Construction And Related Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0365 # 01 Y:2012 | 01 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $20,891 | $900 | Implemented |
LL0358 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,312 | $6,320 | Implemented |
LL0358 # 02 Y:2011 | 02 | 2011 | INSULATE BARE EQUIPMENT | $15,407 | $440 | Implemented |
LL0358 # 04 Y:2011 | 04 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,716 | $45 | Implemented |
TT0075 # 03 Y:2011 | 03 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $47,625 | $21,000 | Implemented |
TT0075 # 04 Y:2011 | 04 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,202 | $14,000 | Implemented |
TT0075 # 05 Y:2011 | 05 | 2011 | INSTALL COMMON HEADER ON COMPRESSORS | $44,869 | $32,200 | Implemented |
TT0075 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,146 | $5,000 | Implemented |
TT0075 # 07 Y:2011 | 07 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,771 | $1,152 | Implemented |
TT0075 # 08 Y:2011 | 08 | 2011 | ISOLATE HOT OR COLD EQUIPMENT | $1,379 | $2,500 | Implemented |
LL0345 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $172,828 | $126,720 | Implemented |
LL0345 # 02 Y:2011 | 02 | 2011 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $44,703 | $4,660 | Implemented |
CO0645 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,890 | $1,290 | Implemented |
CO0645 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,950 | $33,510 | Implemented |
CO0645 # 07 Y:2011 | 07 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $160 | $200 | Implemented |
LL0342 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $45,311 | $5,360 | Implemented |
LL0342 # 03 Y:2011 | 03 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,650 | $490 | Implemented |
LL0342 # 05 Y:2011 | 05 | 2011 | USE PHOTOCELL CONTROLS | $186 | $120 | Implemented |
LL0342 # 06 Y:2011 | 06 | 2011 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $153 | $167 | Implemented |
LL0342 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $45 | $210 | Implemented |
AM0592 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,200 | $11,140 | Implemented |
AM0592 # 03 Y:2011 | 03 | 2011 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $17,240 | $0 | Implemented |
AM0592 # 05 Y:2011 | 05 | 2011 | OPTIMIZE PLANT POWER FACTOR | $6,100 | $14,200 | Implemented |
AM0592 # 06 Y:2011 | 06 | 2011 | INSTALL SKYLIGHTS | $5,600 | $100 | Implemented |
AM0592 # 07 Y:2011 | 07 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,770 | $500 | Implemented |