Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
87
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0224 # 05 Y:2019 | 05 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $14,353 | $500 | Implemented |
TT0224 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,405 | $3,200 | Implemented |
TT0224 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,374 | $16,645 | Implemented |
TT0224 # 08 Y:2019 | 08 | 2019 | USE OPTIMUM THICKNESS INSULATION | $3,722 | $10,752 | Implemented |
TT0224 # 01 Y:2019 | 01 | 2019 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $119,892 | $51,560 | Implemented |
OK0904 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $1,292 | $2,535 | Implemented |
OK0904 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,742 | $950 | Implemented |
OK0904 # 07 Y:2015 | 07 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,742 | $950 | Implemented |
OK0904 # 01 Y:2015 | 01 | 2015 | OPTIMIZE PLANT POWER FACTOR | $4,880 | $14,220 | Implemented |
OK0904 # 11 Y:2015 | 11 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,141 | $1,500 | Implemented |
OK0904 # 02 Y:2015 | 02 | 2015 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $5,563 | $180 | Implemented |
LL0326 # 01 Y:2010 | 01 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $44,220 | $15,480 | Implemented |
LL0326 # 02 Y:2010 | 02 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $31,166 | $6,970 | Implemented |
LL0326 # 03 Y:2010 | 03 | 2010 | INSULATE BARE EQUIPMENT | $13,685 | $3,250 | Implemented |
OK0788 # 10 Y:2010 | 10 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $15,837 | $12,000 | Implemented |
OK0788 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,350 | $8,818 | Implemented |
OK0788 # 01 Y:2010 | 01 | 2010 | INSTALL / REPAIR INSULATION ON STEAM LINES | $285 | $451 | Implemented |
OK0788 # 07 Y:2010 | 07 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,265 | $98,109 | Implemented |
OK0788 # 04 Y:2010 | 04 | 2010 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $3,625 | $1,176 | Implemented |
OK0770 # 07 Y:2008 | 07 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $16,527 | $0 | Implemented |
OK0770 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,686 | $17,885 | Implemented |
OK0770 # 02 Y:2008 | 02 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,597 | $0 | Implemented |
OK0770 # 01 Y:2008 | 01 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,297 | $0 | Implemented |
OK0770 # 03 Y:2008 | 03 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $669 | $1,056 | Implemented |
OK0736 # 03 Y:2006 | 03 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $29,250 | $20,340 | Implemented |