Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
53
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0756 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,116 | $120,000 | Implemented |
OR0756 # 01 Y:2022 | 01 | 2022 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $73,790 | $0 | Implemented |
OR0726 # 02 Y:2019 | 02 | 2019 | REDUCE VENTILATION AIR | $1,259 | $0 | Implemented |
OR0726 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,581 | $7,570 | Implemented |
OR0604 # 01 Y:2013 | 01 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,634 | $500 | Implemented |
OR0604 # 05 Y:2013 | 05 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $11,228 | $11,850 | Implemented |
OR0432 # 04 Y:2003 | 04 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,230 | $7,640 | Implemented |
OR0432 # 03 Y:2003 | 03 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $10,830 | $1,200 | Implemented |
OR0432 # 02 Y:2003 | 02 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $25,900 | $32,000 | Implemented |
OR0388 # 03 Y:2001 | 03 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $108,900 | $60,000 | Implemented |
OR0388 # 01 Y:2001 | 01 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $187,500 | $18,000 | Implemented |
OR0388 # 04 Y:2001 | 04 | 2001 | MODIFY CURRENT INCENTIVE PROGRAM | $368,300 | $29,120 | Implemented |
OR0388 # 02 Y:2001 | 02 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $290,325 | $250,000 | Implemented |
OR0342 # 03 Y:1999 | 03 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $81,500 | $126,000 | Implemented |
OR0342 # 04 Y:1999 | 04 | 1999 | AUTOMATE FINISHING PROCESS | $77,700 | $175,000 | Implemented |
OR0342 # 05 Y:1999 | 05 | 1999 | COMBINE UTILITY METERS | $1,100 | $5,000 | Implemented |
OR0342 # 02 Y:1999 | 02 | 1999 | $22,800 | $7,910 | Implemented | |
OR0342 # 01 Y:1999 | 01 | 1999 | MODIFY CURRENT INCENTIVE PROGRAM | $135,000 | $29,120 | Implemented |
OR0335 # 04 Y:1998 | 04 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $310 | $0 | Implemented |
OR0335 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,045 | $1,000 | Implemented |
OR0313 # 06 Y:1998 | 06 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,060 | $2,670 | Implemented |
OR0313 # 04 Y:1998 | 04 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $6,605 | $0 | Implemented |
OR0313 # 01 Y:1998 | 01 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $59,850 | $437 | Implemented |
OR0267 # 01 Y:1996 | 01 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,697 | $0 | Implemented |
OR0267 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,347 | $3,008 | Implemented |