Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,073
matching recommendationsSIC | 49 | Electric, Gas, And Sanitary Services |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0491 # 06 Y:2020 | 06 | 2020 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $235 | $38 | Implemented |
OK1036 # 01 Y:2020 | 01 | 2020 | INSTALL OCCUPANCY SENSORS | $450 | $1,163 | Implemented |
OK1036 # 04 Y:2020 | 04 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $209 | $1,390 | Implemented |
OK1036 # 05 Y:2020 | 05 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $283 | $312 | Implemented |
UF0554 # 02 Y:2020 | 02 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $19,805 | $25,232 | Implemented |
UF0554 # 03 Y:2020 | 03 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $6,420 | $17,086 | Implemented |
UF0554 # 04 Y:2020 | 04 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $9,363 | $0 | Implemented |
UF0554 # 05 Y:2020 | 05 | 2020 | INSTALL SENSORS TO DETECT DEFECTS | $3,851 | $15,420 | Implemented |
UF0554 # 06 Y:2020 | 06 | 2020 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $30,206 | $6,500 | Implemented |
UF0554 # 07 Y:2020 | 07 | 2020 | USE RE-USABLE FILTERS | $3,000 | $1,906 | Implemented |
UF0553 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,460 | $28,443 | Implemented |
UF0553 # 03 Y:2020 | 03 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,490 | $5,608 | Implemented |
UF0553 # 05 Y:2020 | 05 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $2,236 | $0 | Implemented |
UF0552 # 01 Y:2020 | 01 | 2020 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $23,402 | $0 | Implemented |
UF0552 # 02 Y:2020 | 02 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,039 | $76,500 | Implemented |
UF0552 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,179 | $10,903 | Implemented |
UF0552 # 04 Y:2020 | 04 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,882 | $5,338 | Implemented |
UF0552 # 05 Y:2020 | 05 | 2020 | INSTALL OCCUPANCY SENSORS | $2,364 | $6,394 | Implemented |
UF0552 # 06 Y:2020 | 06 | 2020 | INSTALL AN UNINTERUPTABLE POWER SUPPLY | $45,577 | $65,793 | Implemented |
OK1035 # 01 Y:2020 | 01 | 2020 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,099 | $5,247 | Implemented |
OK1035 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,472 | $6,388 | Implemented |
OK1035 # 04 Y:2020 | 04 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,243 | $4,000 | Implemented |
MA0822 # 01 Y:2020 | 01 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $78,975 | $422,509 | Implemented |
MA0822 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,003 | $6,741 | Implemented |
UK2002 # 01 Y:2020 | 01 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,770 | $2,473 | Implemented |