Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,636
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0819 # 05 Y:2012 | 05 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $15,206 | $29,250 | Implemented |
OK0819 # 07 Y:2012 | 07 | 2012 | INSTALL TIMERS AND/OR THERMOSTATS | $102 | $353 | Implemented |
LL0365 # 01 Y:2012 | 01 | 2012 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $20,891 | $900 | Implemented |
BD0405 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,415 | $7,299 | Implemented |
BD0405 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,286 | $15,356 | Implemented |
BD0405 # 04 Y:2012 | 04 | 2012 | INSTALL OCCUPANCY SENSORS | $2,161 | $1,050 | Implemented |
BD0405 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $82 | $10 | Implemented |
BD0405 # 06 Y:2012 | 06 | 2012 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,704 | $40,000 | Implemented |
MI0214 # 02 Y:2012 | 02 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $4,740 | $2,600 | Implemented |
MI0214 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $986 | $1,320 | Implemented |
MI0214 # 05 Y:2012 | 05 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $948 | $1,058 | Implemented |
UA0072 # 01 Y:2012 | 01 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $17,176 | $2,039 | Implemented |
UA0072 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,742 | $3,900 | Implemented |
UA0072 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,647 | $80 | Implemented |
UD0846 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,212 | $2,054 | Implemented |
UD0846 # 03 Y:2012 | 03 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,567 | $0 | Implemented |
UD0846 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $601 | $1,000 | Implemented |
UD0846 # 08 Y:2012 | 08 | 2012 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $11,712 | $38,000 | Implemented |
SF0405 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,795 | $1,200 | Implemented |
SF0405 # 02 Y:2012 | 02 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $76,949 | $36,149 | Implemented |
SF0405 # 03 Y:2012 | 03 | 2012 | INCREASE AMOUNT OF CONDENSATE RETURNED | $139,563 | $85,532 | Implemented |
SF0405 # 08 Y:2012 | 08 | 2012 | INSTALL OCCUPANCY SENSORS | $3,761 | $9,004 | Implemented |
SF0405 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,215 | $62,332 | Implemented |
BD0404 # 02 Y:2012 | 02 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $31,392 | $76,240 | Implemented |
BD0404 # 04 Y:2012 | 04 | 2012 | INSTALL OCCUPANCY SENSORS | $4,130 | $8,000 | Implemented |