Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
700
matching recommendationsARC | 2.2 | Thermal Systems |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0045 # 08 Y:1994 | 08 | 1994 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,341 | $3,000 | Implemented |
WI0224 # 02 Y:1994 | 02 | 1994 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,980 | $15,000 | n/a |
WI0224 # 01 Y:1994 | 01 | 1994 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $12,194 | $20,000 | n/a |
NC0044 # 01 Y:1994 | 01 | 1994 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $51,000 | $30,000 | Not Implemented |
NC0044 # 04 Y:1994 | 04 | 1994 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $3,593 | $5,000 | Not Implemented |
UL0110 # 03 Y:1994 | 03 | 1994 | INSULATE BARE EQUIPMENT | $1,017 | $205 | n/a |
UD0442 # 06 Y:1994 | 06 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,910 | $10,000 | Implemented |
GT0540 # 03 Y:1994 | 03 | 1994 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,000 | $6,500 | n/a |
GT0540 # 05 Y:1994 | 05 | 1994 | REPAIR AND ELIMINATE STEAM LEAKS | $580 | $100 | n/a |
GT0540 # 06 Y:1994 | 06 | 1994 | INSULATE BARE EQUIPMENT | $3,260 | $17,480 | n/a |
KU0448 # 06 Y:1994 | 06 | 1994 | COVER OPEN TANKS | $99 | $350 | Not Implemented |
KU0448 # 05 Y:1994 | 05 | 1994 | INSULATE BARE EQUIPMENT | $1,200 | $2,295 | Not Implemented |
KU0448 # 03 Y:1994 | 03 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $7,469 | $12,750 | Not Implemented |
KU0448 # 02 Y:1994 | 02 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $11,016 | $10,390 | Not Implemented |
KU0448 # 01 Y:1994 | 01 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $40,898 | $13,400 | Not Implemented |
AS0133 # 06 Y:1994 | 06 | 1994 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $1,424 | $3,000 | Implemented |
GT0539 # 04 Y:1994 | 04 | 1994 | ISOLATE HOT OR COLD EQUIPMENT | $21,350 | $34,500 | Not Implemented |
MA0320 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $8,056 | $4,620 | Not Implemented |
KU0447 # 07 Y:1994 | 07 | 1994 | INSULATE BARE EQUIPMENT | $631 | $497 | Not Implemented |
MS0010 # 04 Y:1994 | 04 | 1994 | USE MINIMUM STEAM OPERATING PRESSURE | $8,352 | $6,000 | Not Implemented |
MS0010 # 05 Y:1994 | 05 | 1994 | INCREASE AMOUNT OF CONDENSATE RETURNED | $7,545 | $15,000 | Not Implemented |
NC0042 # 03 Y:1994 | 03 | 1994 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $176 | $45 | Not Implemented |
NC0042 # 05 Y:1994 | 05 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $505 | $825 | Not Implemented |
KU0449 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $3,928 | $2,300 | Implemented |
IA0100 # 08 Y:1994 | 08 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,056 | $12,220 | Implemented |