IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

269

matching recommendations
Reset
ARC 2.3 Electrical Power
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0253 # 06 Y:1995 06 1995 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $1,958 $0 n/a
GT0575 # 02 Y:1995 02 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,000 $0 Not Implemented
AR0075 # 11 Y:1995 11 1995 OPTIMIZE PLANT POWER FACTOR $25,970 $18,765 Not Implemented
WI0253 # 05 Y:1995 05 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,029 $2,000 n/a
UL0145 # 03 Y:1995 03 1995 OPTIMIZE PLANT POWER FACTOR $30,246 $21,220 Not Implemented
OR0255 # 04 Y:1995 04 1995 OPTIMIZE PLANT POWER FACTOR $1,080 $3,600 Not Implemented
GT0563 # 05 Y:1995 05 1995 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,150 $0 Not Implemented
UD0478 # 01 Y:1995 01 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,144 $0 Not Implemented
UL0143 # 03 Y:1995 03 1995 OPTIMIZE PLANT POWER FACTOR $20,656 $19,584 n/a
WI0255 # 09 Y:1995 09 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $615 $0 n/a
WI0249 # 06 Y:1995 06 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $359 $0 Not Implemented
WI0248 # 05 Y:1995 05 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $656 $2,000 Implemented
WI0250 # 02 Y:1995 02 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,543 $2,000 Implemented
WI0247 # 07 Y:1995 07 1995 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $648 $2,000 Implemented
WI0248 # 08 Y:1995 08 1995 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $488 $0 Implemented
WI0247 # 02 Y:1995 02 1995 USE POWER DURING OFF-PEAK PERIODS $2,146 $1,000 Not Implemented
AR0074 # 05 Y:1995 05 1995 OPTIMIZE PLANT POWER FACTOR $5,669 $13,220 Not Implemented
WI0247 # 04 Y:1995 04 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $888 $2,000 Not Implemented
UM0045 # 05 Y:1995 05 1995 OPTIMIZE PLANT POWER FACTOR $9,291 $14,954 Not Implemented
OK0478 # 08 Y:1995 08 1995 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,578 $1,000 Implemented
UL0142 # 03 Y:1995 03 1995 OPTIMIZE PLANT POWER FACTOR $20,120 $10,918 n/a
OR0254 # 01 Y:1995 01 1995 OPTIMIZE PLANT POWER FACTOR $2,665 $2,500 Not Implemented
ND0231 # 08 Y:1995 08 1995 OPTIMIZE PLANT POWER FACTOR $5,298 $3,780 Not Implemented
AM0254 # 02 Y:1995 02 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,840 $0 Implemented
UL0141 # 04 Y:1995 04 1995 OPTIMIZE PLANT POWER FACTOR $40,228 $19,553 n/a