Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,344
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0472 # 04 Y:1997 | 04 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $410 | $310 | Implemented |
KU0472 # 05 Y:1997 | 05 | 1997 | USE SYNTHETIC LUBRICANT | $320 | $310 | Implemented |
KU0472 # 06 Y:1997 | 06 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $260 | $480 | Implemented |
KU0472 # 07 Y:1997 | 07 | 1997 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $4,740 | $13,000 | Implemented |
KU0472 # 08 Y:1997 | 08 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $66,490 | $21,110 | Implemented |
KU0471 # 01 Y:1996 | 01 | 1996 | PURCHASE HIGH MATERIALS IN RETURNABLE BULK CONTAINERS | $35,724 | $13,720 | Implemented |
KU0471 # 04 Y:1996 | 04 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,101 | $374 | Implemented |
KU0471 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $729 | $1,020 | Implemented |
KU0471 # 08 Y:1996 | 08 | 1996 | USE SYNTHETIC LUBRICANT | $471 | $585 | Implemented |
KU0471 # 09 Y:1996 | 09 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $296 | $1,155 | Implemented |
KU0470 # 01 Y:1996 | 01 | 1996 | CONVERT TO AIR ASSISTED / AIRLESS PAINT GUNS | $181,872 | $5,120 | Implemented |
KU0470 # 02 Y:1996 | 02 | 1996 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $32,289 | $17,350 | Implemented |
KU0470 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,532 | $252 | Implemented |
KU0470 # 04 Y:1996 | 04 | 1996 | INSTALL OCCUPANCY SENSORS | $2,397 | $2,450 | Implemented |
KU0470 # 05 Y:1996 | 05 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $715 | $1,958 | Implemented |
KU0469 # 01 Y:1996 | 01 | 1996 | CONVERT TO AIR ASSISTED / AIRLESS PAINT GUNS | $19,601 | $1,200 | Implemented |
KU0469 # 02 Y:1996 | 02 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,110 | $376 | Implemented |
KU0469 # 03 Y:1996 | 03 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,246 | $15,818 | Implemented |
KU0469 # 07 Y:1996 | 07 | 1996 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,026 | $1,000 | Implemented |
KU0469 # 08 Y:1996 | 08 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $515 | $660 | Implemented |
KU0468 # 01 Y:1996 | 01 | 1996 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $29,684 | $15,000 | Implemented |
KU0468 # 02 Y:1996 | 02 | 1996 | RECOVER AND REUSE COOLING WATER | $4,610 | $8,000 | Implemented |
KU0468 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,860 | $191 | Implemented |
KU0468 # 04 Y:1996 | 04 | 1996 | INSTALL OCCUPANCY SENSORS | $582 | $700 | Implemented |
KU0468 # 05 Y:1996 | 05 | 1996 | INSULATE BARE EQUIPMENT | $566 | $444 | Implemented |