IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

87

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LM0121 # 04 Y:2006 04 2006 INSULATE BARE EQUIPMENT $3,734 $3,100 Implemented
LM0121 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,390 $10,233 Implemented
LM0121 # 02 Y:2006 02 2006 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $91,500 $200 Not Implemented
LM0121 # 01 Y:2006 01 2006 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $183,000 $2,160 Not Implemented
LM0119 # 05 Y:2006 05 2006 CONDENSE OPERATION INTO ONE BUILDING $39,440 $0 Not Implemented
LM0119 # 01 Y:2006 01 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $500 $374 Not Implemented
LM0119 # 02 Y:2006 02 2006 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $746 $0 Not Implemented
LM0119 # 03 Y:2006 03 2006 INSULATE BARE EQUIPMENT $859 $100 Not Implemented
LM0119 # 04 Y:2006 04 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $58,500 $160,200 Not Implemented
LM0119 # 06 Y:2006 06 2006 CONDENSE OPERATION INTO ONE BUILDING $3,375,000 $500,000 Implemented
LM0120 # 01 Y:2006 01 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,819 $0 Implemented
LM0120 # 02 Y:2006 02 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $4,118 $0 Implemented
LM0120 # 03 Y:2006 03 2006 INCREASE AMOUNT OF CONDENSATE RETURNED $50,309 $1,000 Implemented
LM0120 # 04 Y:2006 04 2006 INSULATE BARE EQUIPMENT $20,043 $1,000 Not Implemented
LM0120 # 05 Y:2006 05 2006 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $297,634 $6,380 Not Implemented
LM0120 # 06 Y:2006 06 2006 MODIFY WORKLOAD $47,807 $1,000 Implemented
LM0117 # 05 Y:2006 05 2006 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $6,467 $3,500 Not Implemented
LM0117 # 01 Y:2006 01 2006 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $125,343 $20,000 Implemented
LM0117 # 02 Y:2006 02 2006 INSTALL BACK-UP EQUIPMENT $86,200 $105,000 Implemented
LM0117 # 03 Y:2006 03 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $5,007 $6,550 Not Implemented
LM0117 # 04 Y:2006 04 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $15,788 $3,000 Implemented
LM0117 # 06 Y:2006 06 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $2,061 $500 Implemented
LM0116 # 01 Y:2006 01 2006 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $12,946 $0 Not Implemented
LM0116 # 03 Y:2006 03 2006 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,913 $7,000 Not Implemented
LM0116 # 02 Y:2006 02 2006 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $111,472 $82,700 Implemented