Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,766
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0232 # 03 Y:1992 | 03 | 1992 | REPAIR OR REPLACE STEAM TRAPS | $2,293 | $2 | Implemented |
MA0232 # 04 Y:1992 | 04 | 1992 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $5,067 | $0 | Implemented |
MA0232 # 05 Y:1992 | 05 | 1992 | INCREASE AMOUNT OF CONDENSATE RETURNED | $884 | $150 | Implemented |
MA0233 # 01 Y:1992 | 01 | 1992 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $28,770 | $2,000 | Implemented |
MA0233 # 03 Y:1992 | 03 | 1992 | INSULATE BARE EQUIPMENT | $10,672 | $12,412 | Implemented |
MA0233 # 04 Y:1992 | 04 | 1992 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,341 | $14,210 | Implemented |
MA0233 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,334 | $8,000 | Implemented |
MA0233 # 07 Y:1992 | 07 | 1992 | IMPROVE LUBRICATION PRACTICES | $1,170 | $0 | Implemented |
MA0234 # 01 Y:1992 | 01 | 1992 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $95,700 | $153,525 | Implemented |
MA0234 # 03 Y:1992 | 03 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,505 | $24,600 | Implemented |
MA0234 # 04 Y:1992 | 04 | 1992 | INSTALL / REPAIR INSULATION ON STEAM LINES | $9,100 | $3,720 | Implemented |
MA0231 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,256 | $36 | Implemented |
MA0231 # 07 Y:1992 | 07 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,000 | $0 | Implemented |
MA0228 # 02 Y:1991 | 02 | 1991 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $8,647 | $5,000 | Implemented |
MA0228 # 03 Y:1991 | 03 | 1991 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,534 | $2,000 | Implemented |
MA0228 # 05 Y:1991 | 05 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $891 | $400 | Implemented |
MA0228 # 06 Y:1991 | 06 | 1991 | INSULATE BARE EQUIPMENT | $458 | $430 | Implemented |
MA0229 # 04 Y:1991 | 04 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,388 | $4,900 | Implemented |
MA0229 # 06 Y:1991 | 06 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $520 | $1,749 | Implemented |
MA0229 # 07 Y:1991 | 07 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $430 | $170 | Implemented |
MA0230 # 07 Y:1991 | 07 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,201 | $430 | Implemented |
MA0225 # 04 Y:1991 | 04 | 1991 | INSTALL SET-BACK TIMERS | $1,367 | $660 | Implemented |
MA0225 # 05 Y:1991 | 05 | 1991 | REPAIR OR REPLACE STEAM TRAPS | $970 | $970 | Implemented |
MA0225 # 07 Y:1991 | 07 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $551 | $0 | Implemented |
MA0226 # 01 Y:1991 | 01 | 1991 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $11,242 | $21,238 | Implemented |