Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
936
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0253 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $853 | $288 | Implemented |
MS0253 # 08 Y:2004 | 08 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $198 | $735 | Implemented |
MS0252 # 02 Y:2004 | 02 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,867 | $11,496 | Implemented |
MS0252 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,256 | $230 | Implemented |
MS0252 # 05 Y:2004 | 05 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,270 | $1,731 | Implemented |
MS0252 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $535 | $125 | Implemented |
MS0251 # 02 Y:2004 | 02 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,330 | $1,557 | Implemented |
MS0251 # 03 Y:2004 | 03 | 2004 | USE RADIANT HEATER FOR SPOT HEATING | $4,808 | $9,850 | Implemented |
MS0251 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,806 | $715 | Implemented |
MS0251 # 07 Y:2004 | 07 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $798 | $334 | Implemented |
MS0251 # 09 Y:2004 | 09 | 2004 | USE SYNTHETIC LUBRICANT | $757 | $176 | Implemented |
MS0251 # 10 Y:2004 | 10 | 2004 | DISCONNECT BALLASTS | $260 | $708 | Implemented |
MS0249 # 01 Y:2004 | 01 | 2004 | OPTIMIZE PLANT POWER FACTOR | $54,067 | $26,100 | Implemented |
MS0249 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $19,536 | $250 | Implemented |
MS0249 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,879 | $708 | Implemented |
MS0249 # 11 Y:2004 | 11 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $488 | $820 | Implemented |
MS0246 # 01 Y:2004 | 01 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $29,186 | $4,860 | Implemented |
MS0246 # 07 Y:2004 | 07 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,054 | $158 | Implemented |
MS0246 # 08 Y:2004 | 08 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $868 | $1,063 | Implemented |
MS0246 # 10 Y:2004 | 10 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $176 | $407 | Implemented |
MS0245 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,071 | $156 | Implemented |
MS0245 # 08 Y:2004 | 08 | 2004 | DISCONNECT BALLASTS | $93 | $180 | Implemented |
MS0244 # 01 Y:2004 | 01 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $42,786 | $4,860 | Implemented |
MS0244 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,485 | $247 | Implemented |
MS0244 # 07 Y:2004 | 07 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,004 | $0 | Implemented |