Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,176
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0312 # 09 Y:2005 | 09 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $134 | $100 | Implemented |
NC0310 # 01 Y:2005 | 01 | 2005 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $167,500 | $150,000 | Implemented |
NC0310 # 02 Y:2005 | 02 | 2005 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $97,500 | $61,250 | Implemented |
NC0310 # 03 Y:2005 | 03 | 2005 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $60,000 | $20,500 | Implemented |
NC0310 # 04 Y:2005 | 04 | 2005 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $34,863 | $30,000 | Not Implemented |
NC0310 # 05 Y:2005 | 05 | 2005 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,451 | $3,000 | Implemented |
NC0310 # 06 Y:2005 | 06 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,830 | $875 | Implemented |
NC0310 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $339 | $616 | Not Implemented |
NC0310 # 08 Y:2005 | 08 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $509 | $100 | Implemented |
NC0309 # 01 Y:2005 | 01 | 2005 | ADD ADDITIONAL PRODUCTION SHIFT | $89,630 | $5,000 | Implemented |
NC0309 # 02 Y:2005 | 02 | 2005 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,148 | $21,000 | Implemented |
NC0309 # 03 Y:2005 | 03 | 2005 | MAKE A NEW BY-PRODUCT | $15,600 | $1,000 | Not Implemented |
NC0309 # 04 Y:2005 | 04 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,268 | $6,500 | Implemented |
NC0309 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,767 | $100 | Implemented |
NC0308 # 01 Y:2005 | 01 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,359 | $20,313 | Implemented |
NC0308 # 02 Y:2005 | 02 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,017 | $2,450 | Implemented |
NC0308 # 03 Y:2005 | 03 | 2005 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $15,600 | $1,000 | Not Implemented |
NC0308 # 04 Y:2005 | 04 | 2005 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $13,767 | $6,500 | Implemented |
NC0308 # 05 Y:2005 | 05 | 2005 | ADOPT IN-HOUSE MATERIAL GENERATION | $3,600 | $4,000 | Not Implemented |
NC0308 # 06 Y:2005 | 06 | 2005 | INSTALL OCCUPANCY SENSORS | $1,493 | $2,000 | Implemented |
NC0308 # 07 Y:2005 | 07 | 2005 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $867 | $750 | Implemented |
NC0308 # 08 Y:2005 | 08 | 2005 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $338 | $160 | Implemented |
NC0307 # 01 Y:2004 | 01 | 2004 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $151,225 | $150,000 | Not Implemented |
NC0307 # 02 Y:2004 | 02 | 2004 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $72,400 | $49,500 | Implemented |
NC0307 # 03 Y:2004 | 03 | 2004 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $32,361 | $24,000 | Not Implemented |