Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
803
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0626 # 03 Y:2019 | 03 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $240 | $45 | Not Implemented |
NC0626 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $532 | $871 | Not Implemented |
NC0626 # 04 Y:2019 | 04 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,034 | $135 | Implemented |
NC0626 # 07 Y:2019 | 07 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,977 | $200 | Implemented |
NC0626 # 06 Y:2019 | 06 | 2019 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,170 | $9,000 | Not Implemented |
NC0617 # 04 Y:2018 | 04 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,137 | $12,000 | Implemented |
NC0617 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,647 | $16,472 | Implemented |
NC0617 # 06 Y:2018 | 06 | 2018 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,162 | $50,000 | Implemented |
NC0617 # 05 Y:2018 | 05 | 2018 | RECOVER WASTE HEAT FROM EQUIPMENT | $300 | $1,250 | Not Implemented |
NC0617 # 03 Y:2018 | 03 | 2018 | INSTALL / REPAIR INSULATION ON STEAM LINES | $352 | $90 | Implemented |
NC0617 # 02 Y:2018 | 02 | 2018 | USE PHOTOCELL CONTROLS | $1,341 | $450 | Implemented |
NC0611 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,370 | $200 | Implemented |
NC0611 # 06 Y:2018 | 06 | 2018 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,662 | $200 | Implemented |
NC0611 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $58,179 | $92,653 | Implemented |
NC0611 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,064 | $100 | Not Implemented |
NC0611 # 05 Y:2018 | 05 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $2,887 | $5,685 | Implemented |
NC0611 # 04 Y:2018 | 04 | 2018 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,227 | $35,000 | Not Implemented |
NC0609 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $650 | $200 | Implemented |
NC0609 # 03 Y:2018 | 03 | 2018 | INSTALL OCCUPANCY SENSORS | $173 | $350 | Not Implemented |
NC0609 # 01 Y:2018 | 01 | 2018 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $9,405 | $0 | Not Implemented |
NC0609 # 06 Y:2018 | 06 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $1,705 | $5,685 | Implemented |
NC0609 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,593 | $8,972 | Implemented |
NC0609 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,341 | $2,500 | Implemented |
NC0601 # 06 Y:2017 | 06 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $15,825 | $82,000 | Not Implemented |
NC0601 # 04 Y:2017 | 04 | 2017 | KEEP BOILER TUBES CLEAN | $2,408 | $1,000 | Implemented |