IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,502

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0821 # 08 Y:2012 08 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,301 $0 Implemented
OK0820 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $16,500 $16,200 Implemented
OK0819 # 03 Y:2012 03 2012 INSTALL OCCUPANCY SENSORS $199 $556 Implemented
OK0819 # 04 Y:2012 04 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,633 $560 Implemented
OK0819 # 05 Y:2012 05 2012 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $15,206 $29,250 Implemented
OK0819 # 07 Y:2012 07 2012 INSTALL TIMERS AND/OR THERMOSTATS $102 $353 Implemented
OK0819 # 08 Y:2012 08 2012 INSTALL EQUIPMENT TO MOVE PRODUCT $296,539 $350,000 Implemented
OK0818 # 01 Y:2011 01 2011 USE RADIANT HEATER FOR SPOT HEATING $8,413 $91,000 Implemented
OK0818 # 05 Y:2011 05 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,726 $1,635 Implemented
OK0818 # 08 Y:2011 08 2011 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $482 $2,104 Implemented
OK0817 # 01 Y:2011 01 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,438 $510 Implemented
OK0817 # 07 Y:2011 07 2011 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $5,011 $23,400 Implemented
OK0817 # 10 Y:2011 10 2011 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $3,371 $0 Implemented
OK0816 # 02 Y:2011 02 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $245 $1,488 Implemented
OK0816 # 03 Y:2011 03 2011 INSTALL OCCUPANCY SENSORS $391 $456 Implemented
OK0816 # 08 Y:2011 08 2011 REPLACE BOILER $26,135 $24,220 Implemented
OK0816 # 10 Y:2011 10 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $18,037 $0 Implemented
OK0816 # 11 Y:2011 11 2011 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,760 $1,338 Implemented
OK0815 # 02 Y:2011 02 2011 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $12,351 $0 Implemented
OK0815 # 03 Y:2011 03 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,341 $930 Implemented
OK0815 # 04 Y:2011 04 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $340 $950 Implemented
OK0815 # 09 Y:2011 09 2011 INSULATE BARE EQUIPMENT $3,531 $633 Implemented
OK0814 # 01 Y:2011 01 2011 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $262,832 $1,710,000 Implemented
OK0814 # 02 Y:2011 02 2011 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $189,220 $20,000 Implemented
OK0814 # 03 Y:2011 03 2011 INSTALL EQUIPMENT TO MOVE PRODUCT $1,364,602 $235,960 Implemented