Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,754
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0580 # 02 Y:1999 | 02 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $24,960 | $80,000 | Not Implemented |
OK0580 # 03 Y:1999 | 03 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $35,280 | $140,000 | Not Implemented |
OK0580 # 04 Y:1999 | 04 | 1999 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $840 | $0 | Implemented |
OK0580 # 05 Y:1999 | 05 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $611 | $0 | Implemented |
OK0587 # 01 Y:1999 | 01 | 1999 | INSTALL SYSTEM TO COLLECT SCRAP | $20,078 | $2,250 | n/a |
OK0587 # 02 Y:1999 | 02 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $16,905 | $0 | n/a |
OK0587 # 03 Y:1999 | 03 | 1999 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $7,398 | $31,705 | n/a |
OK0587 # 04 Y:1999 | 04 | 1999 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $3,795 | $0 | n/a |
OK0587 # 05 Y:1999 | 05 | 1999 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,193 | $3,150 | n/a |
OK0587 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $891 | $24 | n/a |
OK0587 # 07 Y:1999 | 07 | 1999 | INSULATE BARE EQUIPMENT | $252 | $1,028 | n/a |
OK0587 # 08 Y:1999 | 08 | 1999 | INSULATE BARE EQUIPMENT | $250 | $525 | n/a |
OK0586 # 01 Y:1999 | 01 | 1999 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,100 | $7,000 | Not Implemented |
OK0586 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,117 | $6,500 | Implemented |
OK0586 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,681 | $1,000 | Implemented |
OK0586 # 04 Y:1999 | 04 | 1999 | USE PRECIPITATING AGENTS IN WASTE WATER TREATMENT THAT PRODUCE THE LEAST QUANTITY OF WASTE | $14,440 | $30,000 | Implemented |
OK0586 # 05 Y:1999 | 05 | 1999 | MOVE PRODUCT USING MECHANICAL MEANS | $81,900 | $50,000 | Not Implemented |
OK0586 # 06 Y:1999 | 06 | 1999 | IMPROVE SPACE COMFORT CONDITIONING | $22,750 | $50,000 | Implemented |
OK0585 # 01 Y:1999 | 01 | 1999 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,155 | $2,668 | n/a |
OK0585 # 02 Y:1999 | 02 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $-1,464 | $4,300 | n/a |
OK0585 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,788 | $0 | n/a |
OK0585 # 04 Y:1999 | 04 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,121 | $1,162 | n/a |
OK0585 # 05 Y:1999 | 05 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $179 | $360 | n/a |
OK0585 # 06 Y:1999 | 06 | 1999 | INSTALL SET-BACK TIMERS | $507 | $260 | n/a |
OK0585 # 07 Y:1999 | 07 | 1999 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $45,623 | $17,000 | n/a |