Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
131
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0165 # 06 Y:1992 | 06 | 1992 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $320 | $824 | Implemented |
OR0165 # 04 Y:1992 | 04 | 1992 | OPTIMIZE PLANT POWER FACTOR | $1,074 | $2,250 | Implemented |
OR0165 # 02 Y:1992 | 02 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,788 | $0 | Implemented |
OR0165 # 05 Y:1992 | 05 | 1992 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $830 | $0 | Implemented |
OR0165 # 01 Y:1992 | 01 | 1992 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $4,045 | $500 | Implemented |
OR0164 # 02 Y:1992 | 02 | 1992 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $1,608 | $0 | Implemented |
OR0164 # 04 Y:1992 | 04 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,042 | $500 | Implemented |
OR0164 # 05 Y:1992 | 05 | 1992 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,127 | $4,466 | Implemented |
OR0164 # 03 Y:1992 | 03 | 1992 | RECOVER MECHANICAL ENERGY | $929 | $0 | Implemented |
OR0163 # 04 Y:1992 | 04 | 1992 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $676 | $1,436 | Implemented |
OR0163 # 06 Y:1992 | 06 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $349 | $0 | Implemented |
OR0163 # 01 Y:1992 | 01 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,055 | $0 | Implemented |
OR0163 # 02 Y:1992 | 02 | 1992 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $1,832 | $360 | Implemented |
OR0163 # 03 Y:1992 | 03 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,260 | $4,000 | Implemented |
OR0162 # 02 Y:1992 | 02 | 1992 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,784 | $2,920 | Implemented |
OR0162 # 04 Y:1992 | 04 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,666 | $5,359 | Implemented |
OR0162 # 06 Y:1992 | 06 | 1992 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $26,207 | $150,000 | Implemented |
OR0162 # 03 Y:1992 | 03 | 1992 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $524 | $750 | Implemented |
OR0160 # 02 Y:1992 | 02 | 1992 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,022,395 | $250,000 | Implemented |
OR0160 # 06 Y:1992 | 06 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $306 | $1,270 | Implemented |
OR0160 # 07 Y:1992 | 07 | 1992 | OPTIMIZE PLANT POWER FACTOR | $13,194 | $10,500 | Implemented |
OR0160 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,017 | $1,244 | Implemented |
OR0161 # 01 Y:1992 | 01 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $384 | $30 | Implemented |
OR0161 # 05 Y:1992 | 05 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $911 | $0 | Implemented |
OR0161 # 04 Y:1992 | 04 | 1992 | INSTALL SET-BACK TIMERS | $4,535 | $0 | Implemented |