Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,959
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0340 # 04 Y:1999 | 04 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $270 | $680 | Not Implemented |
OR0339 # 01 Y:1999 | 01 | 1999 | MOVE PRODUCT USING MECHANICAL MEANS | $5,106,400 | $556,000 | Not Implemented |
OR0339 # 02 Y:1999 | 02 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $6,650 | $24,750 | Implemented |
OR0339 # 03 Y:1999 | 03 | 1999 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $3,080 | $13,800 | Implemented |
OR0339 # 04 Y:1999 | 04 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $178 | $0 | Not Implemented |
OR0339 # 05 Y:1999 | 05 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $730 | $381 | Not Implemented |
OR0339 # 06 Y:1999 | 06 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $254 | $1,000 | Implemented |
OR0339 # 07 Y:1999 | 07 | 1999 | UPGRADE CONTROLS ON COMPRESSORS | $1,508 | $1,454 | Implemented |
OR0339 # 08 Y:1999 | 08 | 1999 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $467 | $441 | Not Implemented |
OR0336 # 01 Y:1999 | 01 | 1999 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $93,600 | $200,000 | Implemented |
OR0336 # 02 Y:1999 | 02 | 1999 | INSTALL SENSORS TO DETECT DEFECTS | $31,700 | $0 | Implemented |
OR0336 # 03 Y:1999 | 03 | 1999 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $27,050 | $8,200 | Not Implemented |
OR0336 # 04 Y:1999 | 04 | 1999 | OPTIMIZE PLANT POWER FACTOR | $3,716 | $10,200 | Not Implemented |
OR0331 # 01 Y:1998 | 01 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,374,400 | $105,000 | Implemented |
OR0331 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,781 | $1,000 | Implemented |
OR0331 # 03 Y:1998 | 03 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $78,861 | $26,602 | Not Implemented |
OR0331 # 04 Y:1998 | 04 | 1998 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $14,990 | $79,750 | Not Implemented |
OR0331 # 05 Y:1998 | 05 | 1998 | OPTIMIZE PLANT POWER FACTOR | $0 | $136,000 | Not Implemented |
OR0337 # 01 Y:1999 | 01 | 1999 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $44,432 | $21,400 | Not Implemented |
OR0337 # 02 Y:1999 | 02 | 1999 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,060 | $0 | Implemented |
OR0337 # 03 Y:1999 | 03 | 1999 | INSULATE BARE EQUIPMENT | $9,949 | $13,663 | Implemented |
OR0337 # 04 Y:1999 | 04 | 1999 | USE LESS WASTEFUL PACKAGING | $34,000 | $73,000 | Not Implemented |
OR0337 # 05 Y:1999 | 05 | 1999 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $11,000 | $28,700 | Implemented |
OR0338 # 01 Y:1999 | 01 | 1999 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $14,000 | $1,630 | Implemented |
OR0338 # 02 Y:1999 | 02 | 1999 | INSTALL AUTOMATIC PACKING EQUIPMENT | $229,748 | $79,349 | Not Implemented |