Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
436
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0633 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,625 | $7,110 | Implemented |
TN0633 # 06 Y:1998 | 06 | 1998 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $270 | $0 | Not Implemented |
TN0633 # 07 Y:1998 | 07 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $9,240 | $18,600 | Not Implemented |
TN0611 # 01 Y:1997 | 01 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $201,410 | $28,000 | Implemented |
TN0611 # 02 Y:1997 | 02 | 1997 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $34,735 | $41,885 | Implemented |
TN0611 # 03 Y:1997 | 03 | 1997 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $9,975 | $9,596 | Not Implemented |
TN0611 # 04 Y:1997 | 04 | 1997 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,330 | $3,240 | Implemented |
TN0611 # 05 Y:1997 | 05 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $860 | $0 | Implemented |
TN0610 # 01 Y:1997 | 01 | 1997 | MODIFY CURRENT INCENTIVE PROGRAM | $118,000 | $10,000 | n/a |
TN0610 # 02 Y:1997 | 02 | 1997 | INSTALL EQUIPMENT TO MOVE PRODUCT | $56,055 | $50,060 | n/a |
TN0610 # 03 Y:1997 | 03 | 1997 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $32,660 | $11,800 | n/a |
TN0610 # 04 Y:1997 | 04 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $15,220 | $3,600 | n/a |
TN0610 # 05 Y:1997 | 05 | 1997 | INSTALL SET-BACK TIMERS | $7,910 | $3,520 | n/a |
TN0610 # 06 Y:1997 | 06 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $630 | $250 | n/a |
TN0610 # 07 Y:1997 | 07 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $525 | $1,120 | n/a |
TN0610 # 08 Y:1997 | 08 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $345 | $250 | n/a |
TN0608 # 01 Y:1997 | 01 | 1997 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $10,600 | $11,400 | Implemented |
TN0608 # 02 Y:1997 | 02 | 1997 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $8,970 | $12,600 | Implemented |
TN0608 # 03 Y:1997 | 03 | 1997 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $4,940 | $2,400 | Not Implemented |
TN0608 # 04 Y:1997 | 04 | 1997 | ELIMINATE THIRD SHIFT | $3,940 | $0 | Not Implemented |
TN0608 # 05 Y:1997 | 05 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $1,300 | $240 | Implemented |
TN0608 # 06 Y:1997 | 06 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $650 | $500 | Implemented |
TN0608 # 07 Y:1997 | 07 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $480 | $0 | Implemented |
TN0608 # 08 Y:1997 | 08 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $170 | $470 | Not Implemented |
TN0604 # 01 Y:1997 | 01 | 1997 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $36,000 | $0 | Implemented |