Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,191
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0243 # 07 Y:1995 | 07 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $898 | $1,796 | Implemented |
BD0029 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,244 | $200 | Implemented |
BD0029 # 08 Y:1995 | 08 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,987 | $4,500 | Implemented |
WI0241 # 03 Y:1995 | 03 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,028 | $1,850 | Implemented |
WI0241 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $473 | $210 | Implemented |
BD0031 # 02 Y:1995 | 02 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,068 | $420 | Implemented |
BD0031 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $234 | $346 | Implemented |
BD0031 # 05 Y:1995 | 05 | 1995 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $87 | $20 | Implemented |
BD0031 # 08 Y:1995 | 08 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,569 | $600 | Implemented |
BD0028 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,733 | $500 | Implemented |
BD0027 # 01 Y:1995 | 01 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,804 | $450 | Implemented |
WI0234 # 05 Y:1995 | 05 | 1995 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $863 | $0 | Implemented |
WI0234 # 06 Y:1995 | 06 | 1995 | CONVERT TO AQUEOUS CLEANING SYSTEM | $26,400 | $18,000 | Implemented |
WI0237 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,436 | $7,500 | Implemented |
WI0237 # 03 Y:1995 | 03 | 1995 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,737 | $0 | Implemented |
WI0237 # 04 Y:1995 | 04 | 1995 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $609 | $0 | Implemented |
WI0237 # 07 Y:1995 | 07 | 1995 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $902 | $0 | Implemented |
BD0026 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,240 | $730 | Implemented |
BD0026 # 03 Y:1995 | 03 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $507 | $20 | Implemented |
BD0025 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,949 | $12,980 | Implemented |
BD0025 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,253 | $400 | Implemented |
BD0025 # 04 Y:1995 | 04 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,558 | $60 | Implemented |
BD0025 # 05 Y:1995 | 05 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,840 | $2,500 | Implemented |
BD0025 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $2,685 | $1,050 | Implemented |
BD0025 # 07 Y:1995 | 07 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,086 | $712 | Implemented |