Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,871
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0115 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,445 | $26,134 | Implemented |
IC0115 # 02 Y:2006 | 02 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,985 | $16,831 | Implemented |
IC0115 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,680 | $65,036 | Implemented |
IC0115 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $272 | $420 | Implemented |
IC0115 # 06 Y:2006 | 06 | 2006 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $54 | $284 | Implemented |
IC0115 # 08 Y:2006 | 08 | 2006 | REPLACE BOILER | $125,042 | $193,200 | Implemented |
IC0115 # 09 Y:2006 | 09 | 2006 | REDUCE EXCESS STEAM BLEEDING | $29,262 | $5,000 | Implemented |
BD0308 # 01 Y:2006 | 01 | 2006 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $55,089 | $7,500 | Implemented |
BD0308 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $16,718 | $15,000 | Implemented |
BD0308 # 03 Y:2006 | 03 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $47,488 | $24,000 | Implemented |
BD0308 # 04 Y:2006 | 04 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,806 | $30,100 | Implemented |
BD0308 # 05 Y:2006 | 05 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,996 | $1,500 | Implemented |
BD0308 # 06 Y:2006 | 06 | 2006 | INSTALL OCCUPANCY SENSORS | $1,394 | $1,275 | Implemented |
BD0308 # 07 Y:2006 | 07 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $161 | $160 | Implemented |
BD0308 # 08 Y:2006 | 08 | 2006 | MINIMIZE WATER USAGE | $254 | $1,150 | Implemented |
UD0735 # 01 Y:2006 | 01 | 2006 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $212,325 | $9,000 | Implemented |
UD0735 # 03 Y:2006 | 03 | 2006 | RECOVER MECHANICAL ENERGY | $33,450 | $32 | Implemented |
UD0735 # 06 Y:2006 | 06 | 2006 | DISCONNECT BALLASTS | $9,527 | $1,440 | Implemented |
UD0735 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $5,203 | $21,789 | Implemented |
UD0735 # 11 Y:2006 | 11 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,665 | $0 | Implemented |
UD0735 # 14 Y:2006 | 14 | 2006 | USE PHOTOCELL CONTROLS | $733 | $308 | Implemented |
UD0735 # 16 Y:2006 | 16 | 2006 | INSULATE BARE EQUIPMENT | $245 | $110 | Implemented |
UD0724 # 03 Y:2005 | 03 | 2005 | USE PHOTOCELL CONTROLS | $16,400 | $0 | Implemented |
UD0724 # 04 Y:2005 | 04 | 2005 | INSULATE BARE EQUIPMENT | $13,563 | $6,505 | Implemented |
UD0724 # 09 Y:2005 | 09 | 2005 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $3,364 | $0 | Implemented |