Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,191
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0033 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,622 | $5,604 | Implemented |
IC0033 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,219 | $1,700 | Implemented |
IC0033 # 07 Y:2002 | 07 | 2002 | USE PLASTIC PALLETS INSTEAD OF WOOD | $10,750 | $22,000 | Implemented |
BD0208 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $79 | $145 | Implemented |
BD0208 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $100 | $400 | Implemented |
IC0032 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $39,454 | $19,500 | Implemented |
BD0207 # 02 Y:2002 | 02 | 2002 | INSTALL OCCUPANCY SENSORS | $2,151 | $825 | Implemented |
BD0207 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $769 | $0 | Implemented |
BD0207 # 08 Y:2002 | 08 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $298 | $400 | Implemented |
BD0206 # 02 Y:2002 | 02 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,599 | $20,080 | Implemented |
BD0206 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,173 | $500 | Implemented |
BD0206 # 08 Y:2002 | 08 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,741 | $2,040 | Implemented |
IC0030 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,316 | $1,400 | Implemented |
IC0030 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,674 | $27,188 | Implemented |
IC0030 # 04 Y:2002 | 04 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,602 | $25,370 | Implemented |
IC0030 # 05 Y:2002 | 05 | 2002 | MODIFY WORKLOAD | $132,950 | $36,600 | Implemented |
BD0205 # 04 Y:2002 | 04 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,089 | $4,800 | Implemented |
BD0205 # 05 Y:2002 | 05 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,003 | $1,000 | Implemented |
BD0205 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,387 | $300 | Implemented |
BD0205 # 10 Y:2002 | 10 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $350 | $360 | Implemented |
IC0029 # 01 Y:2002 | 01 | 2002 | INSULATE BARE EQUIPMENT | $1,907 | $3,610 | Implemented |
IC0029 # 03 Y:2002 | 03 | 2002 | REPAIR AND ELIMINATE STEAM LEAKS | $10,646 | $900 | Implemented |
IC0029 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,828 | $3,000 | Implemented |
IC0029 # 05 Y:2002 | 05 | 2002 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,179 | $1,500 | Implemented |
IC0029 # 06 Y:2002 | 06 | 2002 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $36,712 | $36,036 | Implemented |