IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,622

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK1009 # 07 Y:2019 07 2019 INSTALL TIMERS AND/OR THERMOSTATS $8,182 $1,430 Implemented
OK1001 # 02 Y:2019 02 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,799 $3,509 Implemented
OK0997 # 02 Y:2019 02 2019 INSTALL TIMERS AND/OR THERMOSTATS $17,569 $1,795 Implemented
OK0997 # 04 Y:2019 04 2019 RECOVER WASTE HEAT FROM EQUIPMENT $7,415 $2,668 Implemented
OK0997 # 05 Y:2019 05 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,238 $0 Implemented
OK0997 # 06 Y:2019 06 2019 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,715 $1,306 Implemented
OK0997 # 07 Y:2019 07 2019 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $4,032 $0 Implemented
OK0997 # 08 Y:2019 08 2019 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $1,875 $0 Implemented
OK0997 # 10 Y:2019 10 2019 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $366 $485 Implemented
OK0993 # 01 Y:2018 01 2018 OPTIMIZE PLANT POWER FACTOR $11,376 $41,363 Implemented
OK0993 # 02 Y:2018 02 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $626 $5,696 Implemented
OK0993 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,437 $19,768 Implemented
OK0994 # 01 Y:2018 01 2018 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,051 $590 Implemented
OK0994 # 02 Y:2018 02 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,833 $8,422 Implemented
OK0994 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $15,575 $29,950 Implemented
OK0992 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $308 $259 Implemented
OK0992 # 04 Y:2018 04 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $604 $450 Implemented
OK0992 # 05 Y:2018 05 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $208 $0 Implemented
OK0992 # 06 Y:2018 06 2018 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,701 $15,796 Implemented
OK0992 # 07 Y:2018 07 2018 INSTALL SET-BACK TIMERS $2,280 $1,284 Implemented
OK0992 # 09 Y:2018 09 2018 PAY UTILITY BILLS ON TIME $310 $0 Implemented
OK0990 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,553 $7,440 Implemented
OK0990 # 05 Y:2018 05 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,502 $378 Implemented
OK0989 # 02 Y:2018 02 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $184,161 $201,131 Implemented
OK0989 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,686 $6,881 Implemented