IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

6,403

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AS0180 # 11 Y:1996 11 1996 ELIMINATE LEAKS IN WATER LINES AND VALVES $1,041 $1,780 Implemented
HO0136 # 01 Y:1996 01 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $325 $1,302 Not Implemented
HO0136 # 02 Y:1996 02 1996 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $211 $905 Implemented
HO0136 # 03 Y:1996 03 1996 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $96 $200 Implemented
HO0136 # 04 Y:1996 04 1996 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $47,059 $145,000 Implemented
HO0136 # 05 Y:1996 05 1996 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,736 $6,500 Implemented
IA0145 # 01 Y:1996 01 1996 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $27,015 $50 Not Implemented
IA0145 # 02 Y:1996 02 1996 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,045 $420 Implemented
IA0145 # 03 Y:1996 03 1996 AIR CONDITION ONLY SPACE NECESSARY $43,340 $44,269 Not Implemented
IA0145 # 04 Y:1996 04 1996 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $51,850 $100,800 Not Implemented
IA0145 # 05 Y:1996 05 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $19,046 $65,284 Implemented
IA0145 # 06 Y:1996 06 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,407 $1,998 Implemented
IA0145 # 07 Y:1996 07 1996 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $2,520 $7,060 Implemented
IA0145 # 08 Y:1996 08 1996 RECOVER WASTE HEAT FROM EQUIPMENT $1,764 $2,410 Not Implemented
IA0145 # 09 Y:1996 09 1996 RECOVER WASTE HEAT FROM EQUIPMENT $923 $1,100 Not Implemented
GT0589 # 01 Y:1996 01 1996 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $10,480 $123,250 Implemented
GT0589 # 02 Y:1996 02 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $47,750 $83,090 Implemented
GT0589 # 03 Y:1996 03 1996 USE SYNTHETIC LUBRICANT $6,670 $0 Implemented
GT0589 # 04 Y:1996 04 1996 DISCONNECT BALLASTS $200 $210 Implemented
GT0589 # 05 Y:1996 05 1996 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $8,160 $9,270 Not Implemented
GT0589 # 06 Y:1996 06 1996 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,460 $28,000 Not Implemented
GT0589 # 07 Y:1996 07 1996 PURCHASE HIGH MATERIALS IN RETURNABLE BULK CONTAINERS $147,726 $450,000 Not Implemented
GT0589 # 08 Y:1996 08 1996 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $18,500 $42,700 Not Implemented
AM0279 # 01 Y:1996 01 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,780 $530 Implemented
AM0279 # 02 Y:1996 02 1996 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $950 $490 Implemented