IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,036

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0293 # 14 Y:1997 14 1997 INSTALL OCCUPANCY SENSORS $308 $225 n/a
WI0291 # 01 Y:1997 01 1997 $23,000 $5,000 Not Implemented
WI0291 # 02 Y:1997 02 1997 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,229 $20,892 Implemented
WI0291 # 03 Y:1997 03 1997 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,099 $360 Implemented
WI0291 # 04 Y:1997 04 1997 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $3,451 $10,000 Not Implemented
WI0291 # 05 Y:1997 05 1997 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,429 $740 Not Implemented
WI0291 # 06 Y:1997 06 1997 TURN OFF EQUIPMENT WHEN NOT IN USE $1,693 $0 Implemented
WI0291 # 07 Y:1997 07 1997 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $15,852 $0 Not Implemented
WI0288 # 01 Y:1997 01 1997 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $5,567 $500 Implemented
WI0288 # 02 Y:1997 02 1997 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $2,058 $0 Implemented
WI0288 # 03 Y:1997 03 1997 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,683 $7,800 Not Implemented
WI0288 # 04 Y:1997 04 1997 USE TIGHT-FITTING LIDS ON MATERIAL CONTAINERS TO REDUCE VOC EMISSIONS $1,240 $1,000 Not Implemented
WI0288 # 05 Y:1997 05 1997 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,064 $640 Not Implemented
WI0288 # 06 Y:1997 06 1997 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,008 $5,000 Implemented
WI0288 # 07 Y:1997 07 1997 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $183 $455 Implemented
WI0286 # 01 Y:1997 01 1997 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $29,011 $1,000 Not Implemented
WI0286 # 02 Y:1997 02 1997 REDUCE VENTILATION AIR $6,908 $1,000 Not Implemented
WI0286 # 03 Y:1997 03 1997 USE TIGHT-FITTING LIDS ON MATERIAL CONTAINERS TO REDUCE VOC EMISSIONS $2,999 $1,000 Not Implemented
WI0286 # 04 Y:1997 04 1997 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $2,138 $5,000 Not Implemented
WI0286 # 05 Y:1997 05 1997 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION $26,499 $0 Not Implemented
WI0286 # 06 Y:1997 06 1997 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $19,520 $88,000 Not Implemented
WI0286 # 07 Y:1997 07 1997 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $6,085 $15,000 Not Implemented
WI0286 # 08 Y:1997 08 1997 REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF $2,230 $10,230 Not Implemented
WI0286 # 09 Y:1997 09 1997 INSTALL TIMERS AND/OR THERMOSTATS $18,978 $3,600 Not Implemented
WI0286 # 10 Y:1997 10 1997 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,310 $210 Not Implemented