Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,664
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0122 # 06 Y:1998 | 06 | 1998 | INSULATE FEEDWATER TANK | $56,279 | $15,800 | Not Implemented |
BD0122 # 07 Y:1998 | 07 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $8,070 | $8,000 | Not Implemented |
BD0122 # 08 Y:1998 | 08 | 1998 | $12,828 | $25,000 | Not Implemented | |
BD0122 # 09 Y:1998 | 09 | 1998 | $313 | $0 | Implemented | |
BD0121 # 07 Y:1998 | 07 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $3,914 | $8,000 | Implemented |
BD0121 # 08 Y:1998 | 08 | 1998 | $771 | $500 | Implemented | |
BD0121 # 09 Y:1998 | 09 | 1998 | $404 | $0 | Implemented | |
BD0121 # 01 Y:1998 | 01 | 1998 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,994 | $1,500 | Not Implemented |
BD0121 # 02 Y:1998 | 02 | 1998 | INSTALL OCCUPANCY SENSORS | $1,529 | $675 | Implemented |
BD0121 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,482 | $400 | Not Implemented |
BD0121 # 04 Y:1998 | 04 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,472 | $1,600 | Implemented |
BD0121 # 05 Y:1998 | 05 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $836 | $1,400 | Implemented |
BD0121 # 06 Y:1998 | 06 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $11,391 | $3,000 | Not Implemented |
BD0120 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,459 | $600 | Implemented |
BD0120 # 02 Y:1998 | 02 | 1998 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $4,250 | $4,000 | Not Implemented |
BD0120 # 03 Y:1998 | 03 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,816 | $11,230 | Implemented |
BD0120 # 04 Y:1998 | 04 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,527 | $400 | Not Implemented |
BD0120 # 05 Y:1998 | 05 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,992 | $500 | Not Implemented |
BD0120 # 06 Y:1998 | 06 | 1998 | INSTALL OCCUPANCY SENSORS | $985 | $750 | Not Implemented |
BD0120 # 07 Y:1998 | 07 | 1998 | MINIMIZE WATER USAGE | $1,780 | $750 | Not Implemented |
BD0120 # 08 Y:1998 | 08 | 1998 | $2,430 | $1,000 | Not Implemented | |
BD0120 # 09 Y:1998 | 09 | 1998 | $332 | $0 | Not Implemented | |
BD0119 # 01 Y:1998 | 01 | 1998 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $23,453 | $10,000 | n/a |
BD0119 # 02 Y:1998 | 02 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,670 | $4,000 | n/a |
BD0119 # 03 Y:1998 | 03 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,663 | $3,460 | n/a |