Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
6,403
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0049 # 03 Y:1996 | 03 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $790 | $570 | Implemented |
MS0049 # 04 Y:1996 | 04 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,838 | $80 | Not Implemented |
MS0049 # 05 Y:1996 | 05 | 1996 | USE WATER ON AIR CONDITIONING EXCHANGER TO IMPROVE HEAT TRANSFER AND INCREASE AIR CONDITIONER EFFICIENCY | $2,389 | $5,280 | Not Implemented |
MS0049 # 06 Y:1996 | 06 | 1996 | OPTIMIZE PLANT POWER FACTOR | $1,144 | $900 | Not Implemented |
MS0049 # 07 Y:1996 | 07 | 1996 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $428,130 | $50,000 | Not Implemented |
UF0140 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,090 | $6,861 | Implemented |
UF0140 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,486 | $422 | Implemented |
UF0140 # 03 Y:1996 | 03 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,236 | $0 | Implemented |
UF0140 # 04 Y:1996 | 04 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,087 | $350 | Implemented |
UF0140 # 05 Y:1996 | 05 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $4,400 | $0 | Implemented |
UF0140 # 06 Y:1996 | 06 | 1996 | UPGRADE OBSOLETE EQUIPMENT | $122,659 | $15,000 | Not Implemented |
UD0482 # 01 Y:1996 | 01 | 1996 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $40,000 | $20,000 | Implemented |
UD0482 # 02 Y:1996 | 02 | 1996 | OPTIMIZE PLANT POWER FACTOR | $5,827 | $3,000 | Implemented |
UD0482 # 03 Y:1996 | 03 | 1996 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $40,000 | $10,000 | Not Implemented |
UD0482 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,329 | $7,021 | Not Implemented |
UD0482 # 05 Y:1996 | 05 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $12,397 | $500 | Not Implemented |
UD0482 # 06 Y:1996 | 06 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,360 | $310 | Not Implemented |
TN0571 # 01 Y:1996 | 01 | 1996 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $11,520 | $13,320 | Not Implemented |
TN0571 # 02 Y:1996 | 02 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,933 | $2,100 | Not Implemented |
TN0571 # 03 Y:1996 | 03 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $1,358 | $0 | Not Implemented |
TN0571 # 04 Y:1996 | 04 | 1996 | USE SYNTHETIC LUBRICANT | $748 | $0 | Implemented |
TN0571 # 05 Y:1996 | 05 | 1996 | CONVERT TO AQUEOUS CLEANING SYSTEM | $687 | $1,600 | Implemented |
TN0571 # 06 Y:1996 | 06 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $518 | $600 | Not Implemented |
UF0139 # 01 Y:1996 | 01 | 1996 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $75,430 | $0 | Implemented |
UF0139 # 02 Y:1996 | 02 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $18,648 | $0 | Implemented |