Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,302
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0278 # 13 Y:2008 | 13 | 2008 | INSTALL TIMERS AND/OR THERMOSTATS | $1,785 | $450 | Implemented |
LE0278 # 14 Y:2008 | 14 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $52,373 | $142,010 | Implemented |
OR0535 # 01 Y:2008 | 01 | 2008 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $46,153 | $56,500 | Not Implemented |
OR0535 # 02 Y:2008 | 02 | 2008 | CLEAN STEAM COILS IN PROCESSING TANKS | $6,588 | $1,250 | Not Implemented |
OR0535 # 03 Y:2008 | 03 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $43,923 | $7,200 | Not Implemented |
OR0535 # 04 Y:2008 | 04 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,829 | $47,094 | Not Implemented |
OR0535 # 05 Y:2008 | 05 | 2008 | INSTALL OCCUPANCY SENSORS | $2,286 | $1,850 | Not Implemented |
MI0171 # 01 Y:2008 | 01 | 2008 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $170,598 | $351,000 | Not Implemented |
MI0171 # 02 Y:2008 | 02 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $131,514 | $7,800 | Not Implemented |
MI0171 # 03 Y:2008 | 03 | 2008 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $110,098 | $168,305 | Not Implemented |
MI0171 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $101,069 | $53,922 | Not Implemented |
MI0171 # 05 Y:2008 | 05 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $42,003 | $860 | Not Implemented |
MI0171 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $31,317 | $1,210 | Not Implemented |
OR0533 # 01 Y:2008 | 01 | 2008 | REDUCE SCRAP PRODUCTION | $34,537 | $0 | Implemented |
OR0533 # 02 Y:2008 | 02 | 2008 | USE SOLAR HEAT TO MAKE ELECTRICTY | $19,500 | $157,850 | Not Implemented |
OR0533 # 03 Y:2008 | 03 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,560 | $3,680 | Not Implemented |
OR0533 # 04 Y:2008 | 04 | 2008 | INSTALL OCCUPANCY SENSORS | $7,000 | $44,710 | Not Implemented |
OR0533 # 05 Y:2008 | 05 | 2008 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $8,300 | $2,500 | Implemented |
OR0533 # 06 Y:2008 | 06 | 2008 | OPTIMIZE PLANT POWER FACTOR | $3,400 | $5,075 | Not Implemented |
OR0534 # 01 Y:2008 | 01 | 2008 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $47,698 | $19,250 | Not Implemented |
OR0534 # 02 Y:2008 | 02 | 2008 | REPLACE DC EQUIPMENT WITH AC EQUIPMENT | $7,700 | $167,953 | Not Implemented |
OR0534 # 03 Y:2008 | 03 | 2008 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $6,794 | $0 | Implemented |
OR0534 # 04 Y:2008 | 04 | 2008 | OPTIMIZE PLANT POWER FACTOR | $6,768 | $6,825 | Implemented |
OR0534 # 05 Y:2008 | 05 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $271 | $0 | Implemented |
OR0534 # 06 Y:2008 | 06 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $1,203 | $0 | Not Implemented |