IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

158,455

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0370 # 05 Y:1989 05 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $298 $84 Implemented
GT0370 # 06 Y:1989 06 1989 REPAIR AND ELIMINATE STEAM LEAKS $2,278 $200 Implemented
GT0370 # 07 Y:1989 07 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $415 $150 Implemented
GT0370 # 08 Y:1989 08 1989 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $109,742 $128,000 Implemented
TN0363 # 01 Y:1989 01 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $125,794 $1,200 Implemented
TN0363 # 02 Y:1989 02 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $57,307 $379,000 Implemented
TN0363 # 03 Y:1989 03 1989 INSTALL STEAM TRAP $8,302 $3,450 Implemented
TN0363 # 04 Y:1989 04 1989 USE MINIMUM STEAM OPERATING PRESSURE $3,504 $0 Implemented
TN0363 # 05 Y:1989 05 1989 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,789 $7,480 Implemented
TN0363 # 06 Y:1989 06 1989 KEEP LAMPS AND REFLECTORS CLEAN $6,829 $21,293 Implemented
TN0363 # 07 Y:1989 07 1989 INSTALL SET-BACK TIMERS $2,215 $0 Implemented
TN0363 # 08 Y:1989 08 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,085 $600 Implemented
TN0364 # 01 Y:1989 01 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $139,595 $0 Implemented
TN0364 # 02 Y:1989 02 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $112,374 $757,200 Not Implemented
TN0364 # 03 Y:1989 03 1989 USE MINIMUM STEAM OPERATING PRESSURE $15,272 $0 Not Implemented
TN0364 # 04 Y:1989 04 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $5,471 $800 Implemented
TN0364 # 05 Y:1989 05 1989 CLOSE OFF UNNEEDED STEAM LINES $3,036 $0 Implemented
TN0364 # 06 Y:1989 06 1989 INSTALL SET-BACK TIMERS $3,442 $10,900 Not Implemented
TN0365 # 01 Y:1989 01 1989 KEEP BOILER TUBES CLEAN $1,406 $320 Implemented
TN0365 # 02 Y:1989 02 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $503 $447 Implemented
TN0365 # 03 Y:1989 03 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $431 $225 Implemented
TN0365 # 04 Y:1989 04 1989 USE MINIMUM STEAM OPERATING PRESSURE $384 $0 Implemented
TN0365 # 05 Y:1989 05 1989 INSULATE BARE EQUIPMENT $223 $270 Implemented
TN0365 # 06 Y:1989 06 1989 CLOSE OFF UNNEEDED STEAM LINES $118 $210 Implemented
TN0365 # 07 Y:1989 07 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $95 $1,700 Implemented