IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

158,455

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0057 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $761 $2,402 Not Implemented
OK0057 # 02 Y:1982 02 1982 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $12,500 $500 Implemented
OK0057 # 03 Y:1982 03 1982 OPTIMIZE PLANT POWER FACTOR $20,704 $36,360 Implemented
OK0057 # 04 Y:1982 04 1982 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $6,450 $19,800 Not Implemented
OK0057 # 05 Y:1982 05 1982 COVER OPEN TANKS $640 $655 Implemented
OK0057 # 06 Y:1982 06 1982 INSTALL TIMERS AND/OR THERMOSTATS $4,092 $1,100 Implemented
UD0037 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $935 $379 Not Implemented
UD0037 # 02 Y:1982 02 1982 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $350 $0 Not Implemented
UD0037 # 03 Y:1982 03 1982 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,116 $300 Not Implemented
UD0037 # 04 Y:1982 04 1982 RECOVER WASTE HEAT FROM EQUIPMENT $3,573 $3,500 Implemented
UD0037 # 05 Y:1982 05 1982 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE $1,974 $6,500 Not Implemented
UD0038 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,301 $50 Implemented
UD0038 # 02 Y:1982 02 1982 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $721 $0 Implemented
UD0038 # 03 Y:1982 03 1982 SCHEDULE BAKING TIMES OF SMALL AND LARGE COMPONENTS $3,584 $1,500 Implemented
UD0038 # 04 Y:1982 04 1982 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,327 $300 Implemented
UD0038 # 05 Y:1982 05 1982 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $3,854 $10,000 Implemented
UD0039 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,698 $1,557 Implemented
UD0039 # 02 Y:1982 02 1982 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $480 $0 Implemented
UD0039 # 03 Y:1982 03 1982 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $357 $300 Implemented
UD0039 # 04 Y:1982 04 1982 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $7,302 $13,500 Implemented
UD0039 # 05 Y:1982 05 1982 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS $1,253 $7,000 Implemented
UD0040 # 01 Y:1982 01 1982 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,038 $760 Not Implemented
UD0040 # 02 Y:1982 02 1982 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $176 $300 Implemented
UD0040 # 03 Y:1982 03 1982 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $424 $0 Implemented
UD0040 # 04 Y:1982 04 1982 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $363 $24 Not Implemented