IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

30

matching recommendations
Reset
SIC 38 Instruments And Related Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0517 # 04 Y:2002 04 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,290 $2,740 Implemented
CO0517 # 03 Y:2002 03 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,640 $800 Implemented
AS0333 # 06 Y:2002 06 2002 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL $1,272 $60 Implemented
AS0333 # 01 Y:2002 01 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $597 $20 Implemented
UF0307 # 01 Y:2002 01 2002 INSTALL SPECTRAL REFLECTORS / DELAMP $26,416 $12,233 Implemented
UF0307 # 03 Y:2002 03 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $26,706 $107,644 Implemented
UM0219 # 03 Y:2002 03 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $283 $225 Implemented
UM0219 # 07 Y:2002 07 2002 RECOVER AND REUSE COOLING WATER $8,640 $5,940 Implemented
UM0219 # 06 Y:2002 06 2002 REPLACE BOILER $3,920 $12,000 Implemented
UM0219 # 02 Y:2002 02 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $25,965 $62,826 Implemented
UM0219 # 05 Y:2002 05 2002 TURN OFF EQUIPMENT WHEN NOT IN USE $1,258 $800 Implemented
AS0329 # 05 Y:2002 05 2002 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $591 $737 Implemented
CO0504 # 01 Y:2002 01 2002 USE DEMAND CONTROLLER OR LOAD SHEDDER $3,040 $7,000 Implemented
CO0504 # 04 Y:2002 04 2002 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $44 $44 Implemented
CO0504 # 03 Y:2002 03 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $371 $0 Implemented
CO0504 # 02 Y:2002 02 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,250 $1,950 Implemented
OK0638 # 02 Y:2002 02 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,120 $6,442 Implemented
OK0638 # 03 Y:2002 03 2002 INSTALL OCCUPANCY SENSORS $1,798 $862 Implemented
OK0638 # 06 Y:2002 06 2002 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $623 $1,067 Implemented
SU0136 # 02 Y:2002 02 2002 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $6,245 $0 Implemented
SU0136 # 08 Y:2002 08 2002 TURN OFF EQUIPMENT WHEN NOT IN USE $1,654 $0 Implemented
SU0136 # 11 Y:2002 11 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $928 $63 Implemented
SU0136 # 12 Y:2002 12 2002 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $928 $0 Implemented
SU0136 # 13 Y:2002 13 2002 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $379 $5 Implemented
SU0136 # 14 Y:2002 14 2002 TURN OFF EQUIPMENT WHEN NOT IN USE $219 $0 Implemented