IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

379

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0712 # 07 Y:2005 07 2005 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $2,166 $525 Implemented
UD0712 # 08 Y:2005 08 2005 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $1,616 $1,000 Not Implemented
UD0712 # 09 Y:2005 09 2005 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $1,498 $0 Not Implemented
UD0712 # 10 Y:2005 10 2005 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $953 $0 Not Implemented
UD0712 # 11 Y:2005 11 2005 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $259 $1,000 Implemented
UD0711 # 01 Y:2005 01 2005 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER $343,339 $10,000 Not Implemented
UD0711 # 02 Y:2005 02 2005 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $143,601 $246,784 Not Implemented
UD0711 # 03 Y:2005 03 2005 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT $113,328 $400,000 Not Implemented
UD0711 # 04 Y:2005 04 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $23,341 $80,215 Not Implemented
UD0711 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,813 $2,025 Implemented
UD0711 # 06 Y:2005 06 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,651 $1,240 Implemented
UD0711 # 07 Y:2005 07 2005 UPGRADE CONTROLS ON COMPRESSORS $4,427 $600 Not Implemented
UD0711 # 08 Y:2005 08 2005 INSULATE BARE EQUIPMENT $1,305 $3,530 Implemented
UM0274 # 01 Y:2005 01 2005 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $42,936 $135,000 Not Implemented
UM0274 # 02 Y:2005 02 2005 RECOVER WASTE HEAT FROM EQUIPMENT $5,622 $2,000 Not Implemented
UM0274 # 03 Y:2005 03 2005 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $3,242 $0 Implemented
UM0274 # 04 Y:2005 04 2005 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,966 $200 Not Implemented
UM0274 # 05 Y:2005 05 2005 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,699 $700 Not Implemented
UM0274 # 06 Y:2005 06 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $791 $2,000 Not Implemented
UM0272 # 01 Y:2005 01 2005 RECOVER WASTE HEAT FROM EQUIPMENT $2,828 $1,000 Implemented
UM0272 # 02 Y:2005 02 2005 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $2,313 $3,000 Not Implemented
UM0272 # 03 Y:2005 03 2005 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $2,631 $300 Implemented
UM0272 # 04 Y:2005 04 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,459 $5,009 Not Implemented
UD0709 # 01 Y:2005 01 2005 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $17,133 $0 Not Implemented
UD0709 # 02 Y:2005 02 2005 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $13,549 $34,600 Not Implemented