Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
770
matching recommendationsNAICS | 22132 | Sewage Treatment Facilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0540 # 04 Y:2022 | 04 | 2022 | INSTALL TIMERS AND/OR THERMOSTATS | $395 | $1,341 | Implemented |
AS0540 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,767 | $4,200 | Implemented |
AS0540 # 02 Y:2022 | 02 | 2022 | PAY BILLS ON TIME TO AVOID LATE FEES | $9,085 | $21 | Implemented |
TR0036 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $678 | $755 | Implemented |
WM0191 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $733 | $0 | Implemented |
WM0191 # 04 Y:2023 | 04 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,985 | $2,600 | Implemented |
WM0191 # 02 Y:2023 | 02 | 2023 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $16,731 | $32,670 | Implemented |
WM0190 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $236 | $1,000 | Implemented |
WM0190 # 02 Y:2023 | 02 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $3,068 | $525 | Implemented |
DL0216 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $124,500 | $181,000 | Implemented |
DL0216 # 03 Y:2023 | 03 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $93,960 | $250,000 | Implemented |
DL0216 # 05 Y:2023 | 05 | 2023 | BURN A LESS EXPENSIVE GRADE OF FUEL | $48,610 | $0 | Implemented |
DL0216 # 06 Y:2023 | 06 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,154 | $50,000 | Implemented |
DL0216 # 07 Y:2023 | 07 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,672 | $0 | Implemented |
LS2304 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,461 | $3,167 | Implemented |
LS2304 # 04 Y:2023 | 04 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,867 | $56,400 | Implemented |
LS2304 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $158 | $125 | Implemented |
LS2303 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,702 | $4,916 | Implemented |
LS2303 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $1,420 | $200 | Implemented |
LS2303 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $29,491 | $99,000 | Implemented |
AM0866 # 02 Y:2023 | 02 | 2023 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $6,607 | $4,020 | Implemented |
AM0866 # 04 Y:2023 | 04 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $780 | $0 | Implemented |
AM0866 # 05 Y:2023 | 05 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $630 | $3,605 | Implemented |
AM0866 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $510 | $2,441 | Implemented |
AM0866 # 07 Y:2023 | 07 | 2023 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $36 | $18 | Implemented |