Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
99
matching recommendationsNAICS | 324121 | Asphalt Paving Mixture and Block Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0713 # 04 Y:2018 | 04 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $7,018 | $26,371 | Implemented |
OR0713 # 05 Y:2018 | 05 | 2018 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,108 | $5,028 | Implemented |
MA0785 # 01 Y:2017 | 01 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,893 | $20,000 | Implemented |
MA0785 # 03 Y:2017 | 03 | 2017 | KEEP BOILER TUBES CLEAN | $1,014 | $1,200 | Implemented |
OR0680 # 04 Y:2017 | 04 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,732 | $3,529 | Implemented |
OR0680 # 01 Y:2017 | 01 | 2017 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $45,000 | $66,392 | Implemented |
OR0680 # 03 Y:2017 | 03 | 2017 | ADJUST BURNERS FOR EFFICIENT OPERATION | $2,467 | $1,000 | Implemented |
MI0249 # 03 Y:2013 | 03 | 2013 | INCREASE EFFICIENCY OF TRUCKS | $14,224 | $11,600 | Implemented |
MI0249 # 05 Y:2013 | 05 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,223 | $2,520 | Implemented |
MI0249 # 06 Y:2013 | 06 | 2013 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $2,451 | $347 | Implemented |
MI0249 # 07 Y:2013 | 07 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,546 | $1,660 | Implemented |
MI0249 # 08 Y:2013 | 08 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,904 | $80 | Implemented |
MI0249 # 01 Y:2013 | 01 | 2013 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $1,845,922 | $2,000,000 | Implemented |
MI0247 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,027 | $8,010 | Implemented |
MI0247 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,525 | $1,660 | Implemented |
MI0247 # 06 Y:2013 | 06 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,908 | $2,520 | Implemented |
MI0247 # 08 Y:2013 | 08 | 2013 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $870 | $347 | Implemented |
SU0335 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,709 | $5,124 | Implemented |
SU0335 # 03 Y:2013 | 03 | 2013 | BURN A LESS EXPENSIVE GRADE OF FUEL | $288,725 | $218,600 | Implemented |
SU0335 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $866 | $2,820 | Implemented |
UM0416 # 02 Y:2012 | 02 | 2012 | INSTALL OCCUPANCY SENSORS | $222 | $450 | Implemented |
IA0390 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,305 | $896 | Implemented |
IA0390 # 04 Y:2006 | 04 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $8,812 | $3,600 | Implemented |
IA0390 # 01 Y:2006 | 01 | 2006 | ADJUST BURNERS FOR EFFICIENT OPERATION | $53,488 | $1,000 | Implemented |
SF0322 # 02 Y:2006 | 02 | 2006 | INSULATE BARE EQUIPMENT | $19,058 | $11,866 | Implemented |