Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,659
matching recommendationsNAICS | 32619 | Other Plastics Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0566 # 04 Y:2018 | 04 | 2018 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,029 | $500 | Implemented |
WV0566 # 06 Y:2018 | 06 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,581 | $575 | Implemented |
WV0566 # 07 Y:2018 | 07 | 2018 | MINIMIZE WATER USAGE | $1,217 | $3,150 | Implemented |
WV0566 # 09 Y:2018 | 09 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $595 | $50 | Implemented |
WV0566 # 10 Y:2018 | 10 | 2018 | INSULATE BARE EQUIPMENT | $114 | $180 | Implemented |
NC0620 # 01 Y:2018 | 01 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,189 | $2,250 | Implemented |
NC0620 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,426 | $100 | Implemented |
NC0620 # 05 Y:2018 | 05 | 2018 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $927 | $1,000 | Implemented |
OK0992 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $308 | $259 | Implemented |
OK0992 # 04 Y:2018 | 04 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $604 | $450 | Implemented |
OK0992 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $208 | $0 | Implemented |
OK0992 # 06 Y:2018 | 06 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,701 | $15,796 | Implemented |
OK0992 # 07 Y:2018 | 07 | 2018 | INSTALL SET-BACK TIMERS | $2,280 | $1,284 | Implemented |
OK0992 # 09 Y:2018 | 09 | 2018 | PAY UTILITY BILLS ON TIME | $310 | $0 | Implemented |
NC0615 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,150 | $25,474 | Implemented |
NC0615 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,044 | $165 | Implemented |
NC0615 # 07 Y:2018 | 07 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $5,240 | $12,129 | Implemented |
NC0615 # 10 Y:2018 | 10 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $282 | $50 | Implemented |
WV0563 # 04 Y:2018 | 04 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $20,002 | $754 | Implemented |
WV0563 # 06 Y:2018 | 06 | 2018 | MINIMIZE WATER USAGE | $1,202 | $1,400 | Implemented |
WV0563 # 07 Y:2018 | 07 | 2018 | INSULATE BARE EQUIPMENT | $264 | $235 | Implemented |
IP0106 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $548 | $1,325 | Implemented |
IP0106 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,159 | $21,897 | Implemented |
OK0985 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,240 | $19,498 | Implemented |
OK0985 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,769 | $21,562 | Implemented |