Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
567
matching recommendationsNAICS | 3262 | Rubber Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0456 # 08 Y:2012 | 08 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,790 | $600 | Implemented |
SD0456 # 10 Y:2012 | 10 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,050 | $200 | Implemented |
WV0455 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,439 | $5,745 | Implemented |
WV0455 # 04 Y:2012 | 04 | 2012 | INSULATE BARE EQUIPMENT | $6,023 | $2,440 | Implemented |
WV0455 # 06 Y:2012 | 06 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,600 | $3,294 | Implemented |
WV0455 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,863 | $1,706 | Implemented |
WV0455 # 10 Y:2012 | 10 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,663 | $2,117 | Implemented |
WV0455 # 11 Y:2012 | 11 | 2012 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,644 | $1,000 | Implemented |
WV0455 # 12 Y:2012 | 12 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,418 | $1,000 | Implemented |
WV0455 # 13 Y:2012 | 13 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $1,157 | $841 | Implemented |
WV0455 # 15 Y:2012 | 15 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $845 | $70 | Implemented |
WV0455 # 16 Y:2012 | 16 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $712 | $620 | Implemented |
WV0455 # 17 Y:2012 | 17 | 2012 | USE PHOTOCELL CONTROLS | $645 | $620 | Implemented |
WV0455 # 18 Y:2012 | 18 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $377 | $500 | Implemented |
UD0863 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,407 | $16,259 | Implemented |
UD0863 # 04 Y:2012 | 04 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $557 | $0 | Implemented |
UD0863 # 07 Y:2012 | 07 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $16,249 | $0 | Implemented |
UD0863 # 09 Y:2012 | 09 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,856 | $1,000 | Implemented |
UD0863 # 10 Y:2012 | 10 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $13,284 | $0 | Implemented |
UD0863 # 11 Y:2012 | 11 | 2012 | REPAIR OR REPLACE STEAM TRAPS | $10,008 | $2,600 | Implemented |
UD0863 # 13 Y:2012 | 13 | 2012 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $43,532 | $0 | Implemented |
UA0085 # 02 Y:2012 | 02 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $164,656 | $57,024 | Implemented |
UA0085 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $151,364 | $35,390 | Implemented |
UA0085 # 07 Y:2012 | 07 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $58,443 | $1,920 | Implemented |
UD0859 # 02 Y:2012 | 02 | 2012 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $581 | $600 | Implemented |