Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,975
matching recommendationsNAICS | 331 | Primary Metal Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0184 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,216 | $17,960 | Implemented |
IP0184 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,142 | $12,019 | Implemented |
IC0296 # 01 Y:2024 | 01 | 2024 | INSULATE BARE EQUIPMENT | $5,921 | $1,066 | Implemented |
IC0296 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,777 | $8,406 | Implemented |
IC0296 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,324 | $400 | Implemented |
IC0296 # 06 Y:2024 | 06 | 2024 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $10,898 | $23,884 | Implemented |
IC0296 # 09 Y:2024 | 09 | 2024 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $62,421 | $0 | Implemented |
IC0296 # 11 Y:2024 | 11 | 2024 | INSULATE BARE EQUIPMENT | $2,446 | $608 | Implemented |
IC0296 # 12 Y:2024 | 12 | 2024 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,022 | $1,150 | Implemented |
IC0296 # 13 Y:2024 | 13 | 2024 | REPAIR OR REPLACE STEAM TRAPS | $7,154 | $1,011 | Implemented |
MZ0355 # 07 Y:2023 | 07 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,043 | $320 | Implemented |
AS0565 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $583,260 | $500 | Implemented |
AS0565 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $139,376 | $1,265,613 | Implemented |
AS0565 # 05 Y:2023 | 05 | 2023 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $1,336 | $75 | Implemented |
AS0565 # 07 Y:2023 | 07 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $454 | $720 | Implemented |
WM0207 # 05 Y:2024 | 05 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,225 | $1,100 | Implemented |
WM0207 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,028 | $12,825 | Implemented |
WM0207 # 03 Y:2024 | 03 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,619 | $4,084 | Implemented |
SD0643 # 07 Y:2024 | 07 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $489 | $250 | Implemented |
SD0643 # 04 Y:2024 | 04 | 2024 | USE OPTIMUM TEMPERATURE | $6,846 | $0 | Implemented |
SD0643 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $338 | $424 | Implemented |
MZ0352 # 10 Y:2023 | 10 | 2023 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $49,532 | $3,900 | Implemented |
MZ0352 # 09 Y:2023 | 09 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,760 | $3,671 | Implemented |
MZ0352 # 08 Y:2023 | 08 | 2023 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $38,678 | $132,100 | Implemented |
MZ0352 # 07 Y:2023 | 07 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,709 | $750 | Implemented |