Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
468
matching recommendationsNAICS | 33211 | Forging and Stamping |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0324 # 02 Y:2007 | 02 | 2007 | USE RADIANT HEATER FOR SPOT HEATING | $17,557 | $16,000 | Implemented |
BD0324 # 03 Y:2007 | 03 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,458 | $4,133 | Implemented |
BD0324 # 04 Y:2007 | 04 | 2007 | USE PHOTOCELL CONTROLS | $594 | $200 | Implemented |
BD0324 # 05 Y:2007 | 05 | 2007 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $526 | $300 | Implemented |
BD0324 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $219 | $270 | Implemented |
BD0324 # 07 Y:2007 | 07 | 2007 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $1,688 | $2,500 | Implemented |
WV0355 # 03 Y:2007 | 03 | 2007 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $63,700 | $65,000 | Implemented |
WV0355 # 05 Y:2007 | 05 | 2007 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $24,887 | $25,000 | Implemented |
WV0355 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $17,682 | $6,140 | Implemented |
WV0355 # 08 Y:2007 | 08 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,654 | $39,137 | Implemented |
WV0355 # 09 Y:2007 | 09 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $9,370 | $5,220 | Implemented |
WV0355 # 10 Y:2007 | 10 | 2007 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,946 | $4,000 | Implemented |
WV0355 # 13 Y:2007 | 13 | 2007 | DEVELOP A REPAIR/REPLACE POLICY | $5,152 | $1,973 | Implemented |
WV0355 # 15 Y:2007 | 15 | 2007 | INSTALL OCCUPANCY SENSORS | $2,673 | $2,890 | Implemented |
WV0355 # 16 Y:2007 | 16 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,450 | $0 | Implemented |
WV0355 # 17 Y:2007 | 17 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,148 | $2,700 | Implemented |
UD0746 # 02 Y:2006 | 02 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $20,324 | $10,000 | Implemented |
UD0746 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $19,239 | $7,105 | Implemented |
UD0746 # 04 Y:2006 | 04 | 2006 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $6,408 | $0 | Implemented |
UD0746 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,123 | $1,530 | Implemented |
MA0606 # 08 Y:2006 | 08 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $130,688 | $6,000 | Implemented |
WI0515 # 02 Y:2006 | 02 | 2006 | ELIMINATE SHIFT | $10,200 | $0 | Implemented |
WI0515 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,559 | $0 | Implemented |
WI0515 # 05 Y:2006 | 05 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,038 | $1,280 | Implemented |
WV0339 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,620 | $11,160 | Implemented |