Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsNAICS | 332811 | Metal Heat Treating |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0024 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $490 | $0 | Implemented |
SJ0024 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,182 | $0 | Implemented |
SJ0024 # 06 Y:2024 | 06 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,248 | $0 | Implemented |
SJ0024 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,292 | $8,243 | Implemented |
SD0635 # 09 Y:2023 | 09 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $1,894 | $3,900 | Implemented |
SD0635 # 08 Y:2023 | 08 | 2023 | REPAIR AND ELIMINATE STEAM LEAKS | $5,330 | $3,125 | Implemented |
SD0635 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $541 | $1,832 | Implemented |
SD0635 # 06 Y:2023 | 06 | 2023 | ADJUST BURNERS FOR EFFICIENT OPERATION | $10,368 | $0 | Implemented |
SD0635 # 04 Y:2023 | 04 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $22,128 | $51,000 | Implemented |
SD0635 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,458 | $1,000 | Implemented |
SD0635 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $77,202 | $252,463 | Implemented |
SF0444 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $404 | $1,967 | Implemented |
LM0092 # 07 Y:2005 | 07 | 2005 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $19,657 | $5,000 | Implemented |
LM0092 # 08 Y:2005 | 08 | 2005 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $36,180 | $5,000 | Implemented |
LM0092 # 09 Y:2005 | 09 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $98,438 | $100,000 | Implemented |
LM0092 # 10 Y:2005 | 10 | 2005 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $14,473 | $100 | Implemented |
LM0092 # 11 Y:2005 | 11 | 2005 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $1,200 | $100 | Implemented |
LM0092 # 06 Y:2005 | 06 | 2005 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $12,597 | $5,000 | Implemented |
LM0092 # 05 Y:2005 | 05 | 2005 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $62,655 | $140,000 | Implemented |
LM0092 # 03 Y:2005 | 03 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,281 | $170 | Implemented |
SF0289 # 06 Y:2004 | 06 | 2004 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $270 | $885 | Implemented |
SF0289 # 02 Y:2004 | 02 | 2004 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $956 | $180 | Implemented |
SF0289 # 01 Y:2004 | 01 | 2004 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $2,527 | $2,527 | Implemented |
SF0289 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,750 | $6,748 | Implemented |
LM0074 # 05 Y:2004 | 05 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $3,618 | $4,000 | Implemented |