Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,737
matching recommendationsNAICS | 333 | Machinery Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LL0191 # 09 Y:2004 | 09 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,500 | $60 | Implemented |
LL0191 # 10 Y:2004 | 10 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $792 | $237 | Implemented |
IA0343 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,846 | $446 | Implemented |
IA0343 # 03 Y:2004 | 03 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $125 | $70 | Implemented |
IA0343 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,173 | $7,306 | Implemented |
IA0343 # 07 Y:2004 | 07 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $39,733 | $10,000 | Implemented |
MS0253 # 03 Y:2004 | 03 | 2004 | USE RADIANT HEATER FOR SPOT HEATING | $1,526 | $4,000 | Implemented |
MS0253 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $853 | $288 | Implemented |
MS0253 # 08 Y:2004 | 08 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $198 | $735 | Implemented |
OK0691 # 02 Y:2004 | 02 | 2004 | EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | $270,439 | $2,825 | Implemented |
OK0691 # 03 Y:2004 | 03 | 2004 | INSTALL SET-BACK TIMERS | $6,531 | $3,832 | Implemented |
OK0691 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,036 | $559 | Implemented |
OK0691 # 05 Y:2004 | 05 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $265 | $0 | Implemented |
OK0691 # 07 Y:2004 | 07 | 2004 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $886 | $139 | Implemented |
SU0188 # 01 Y:2004 | 01 | 2004 | ADVERTISE PRODUCT OR SERVICE | $10,418 | $0 | Implemented |
SU0188 # 02 Y:2004 | 02 | 2004 | PAY UTILITY BILLS ON TIME | $1,203 | $0 | Implemented |
UD0698 # 01 Y:2004 | 01 | 2004 | REDUCE FLUID FLOW RATES | $12,697 | $0 | Implemented |
UD0698 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,898 | $1,635 | Implemented |
UD0698 # 06 Y:2004 | 06 | 2004 | IMPROVE LUBRICATION PRACTICES | $1,693 | $0 | Implemented |
UD0698 # 07 Y:2004 | 07 | 2004 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $739 | $845 | Implemented |
UD0698 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $84 | $270 | Implemented |
NC0286 # 02 Y:2004 | 02 | 2004 | REDUCE VENTILATION AIR | $12,177 | $35,730 | Implemented |
NC0286 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,904 | $100 | Implemented |
NC0286 # 04 Y:2004 | 04 | 2004 | UPGRADE CONTROLS ON COMPRESSORS | $1,892 | $2,000 | Implemented |
NC0286 # 07 Y:2004 | 07 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $175 | $169 | Implemented |