Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
129
matching recommendationsNAICS | 333517 | Machine Tool Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0213 # 01 Y:2024 | 01 | 2024 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $10,341 | $20,389 | Implemented |
WM0213 # 04 Y:2024 | 04 | 2024 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,240 | $2,590 | Implemented |
WM0213 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,049 | $125 | Implemented |
MZ0307 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $809 | $1,130 | Implemented |
MZ0307 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,100 | $6,233 | Implemented |
NC0644 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,841 | $25,826 | Implemented |
NC0644 # 01 Y:2019 | 01 | 2019 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $28,909 | $65,575 | Implemented |
NC0644 # 02 Y:2019 | 02 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $23,191 | $30,000 | Implemented |
SU0473 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $192 | $290 | Implemented |
SU0473 # 03 Y:2019 | 03 | 2019 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $519 | $200 | Implemented |
SU0473 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,790 | $0 | Implemented |
UD0982 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,010 | $500 | Implemented |
UD0982 # 01 Y:2018 | 01 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $21,886 | $0 | Implemented |
UD0982 # 02 Y:2018 | 02 | 2018 | REDUCE VENTILATION AIR | $9,420 | $3,000 | Implemented |
UD0982 # 10 Y:2018 | 10 | 2018 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $5,443 | $0 | Implemented |
UD0982 # 06 Y:2018 | 06 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,208 | $3,500 | Implemented |
UD0982 # 13 Y:2018 | 13 | 2018 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $13,372 | $10,000 | Implemented |
UD0982 # 05 Y:2018 | 05 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,501 | $8,000 | Implemented |
UD0982 # 04 Y:2018 | 04 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,415 | $0 | Implemented |
UD0982 # 11 Y:2018 | 11 | 2018 | INSTALL OCCUPANCY SENSORS | $5,167 | $1,500 | Implemented |
UD0982 # 12 Y:2018 | 12 | 2018 | ADD AREA LIGHTING SWITCHES | $675 | $500 | Implemented |
UD0960 # 03 Y:2017 | 03 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $10,808 | $0 | Implemented |
UD0960 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,385 | $0 | Implemented |
UD0960 # 06 Y:2017 | 06 | 2017 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $514 | $1,425 | Implemented |
UD0960 # 05 Y:2017 | 05 | 2017 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $17,273 | $0 | Implemented |