IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

39

matching recommendations
Reset
NAICS 335 Electrical Equipment, Appliance, and Component Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IC0122 # 06 Y:2006 06 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $490 $0 Implemented
IC0122 # 05 Y:2006 05 2006 INSTALL OCCUPANCY SENSORS $1,480 $1,791 Implemented
IC0122 # 04 Y:2006 04 2006 INSTALL TIMERS AND/OR THERMOSTATS $2,700 $0 Implemented
IC0122 # 01 Y:2006 01 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $14,489 $58,358 Implemented
IC0119 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,829 $600 Implemented
IC0119 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $34,559 $114,725 Implemented
IC0119 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $25,402 $61,775 Implemented
IC0119 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,048 $38,744 Implemented
OK0736 # 01 Y:2006 01 2006 INSULATE BARE EQUIPMENT $224,746 $154,440 Implemented
OK0736 # 03 Y:2006 03 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $29,250 $20,340 Implemented
OK0736 # 04 Y:2006 04 2006 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $8,438 $765 Implemented
OK0736 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,322 $1,267 Implemented
MS0300 # 01 Y:2006 01 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $183,533 $1,062 Implemented
MS0300 # 02 Y:2006 02 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,150 $123,600 Implemented
WV0345 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,346 $2,805 Implemented
WV0345 # 12 Y:2006 12 2006 DEVELOP A REPAIR/REPLACE POLICY $5,468 $800 Implemented
WV0345 # 10 Y:2006 10 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,809 $49,405 Implemented
WV0345 # 08 Y:2006 08 2006 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $9,402 $1,000 Implemented
WV0345 # 06 Y:2006 06 2006 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $14,670 $1,000 Implemented
WV0345 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,574 $60,657 Implemented
WV0343 # 03 Y:2006 03 2006 INSULATE BARE EQUIPMENT $21,955 $3,114 Implemented
WV0343 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $18,918 $0 Implemented
WV0343 # 06 Y:2006 06 2006 DEVELOP A REPAIR/REPLACE POLICY $4,236 $635 Implemented
WI0517 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,406 $37,744 Implemented
WI0517 # 05 Y:2006 05 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $5,306 $500 Implemented