IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

511

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0513 # 07 Y:2017 07 2017 INSTALL / REPAIR INSULATION ON STEAM LINES $2,443 $1,481 Implemented
UF0513 # 02 Y:2017 02 2017 ISOLATE HOT OR COLD EQUIPMENT $25,893 $3,150 Implemented
UF0513 # 03 Y:2017 03 2017 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $14,487 $23,157 Implemented
UF0513 # 01 Y:2017 01 2017 REPLACE BOILER $38,664 $30,000 Not Implemented
LS0012 # 01 Y:2017 01 2017 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $28,766 $12,000 Not Implemented
LS0012 # 03 Y:2017 03 2017 INSULATE BARE EQUIPMENT $993 $548 Not Implemented
GT0908 # 04 Y:2017 04 2017 INSTALL ISOLATION TRANSFORMER ON ADJUSTABLE FREQUENCY DRIVE $30,382 $47,492 Not Implemented
GT0908 # 02 Y:2017 02 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,577 $578 Implemented
GT0908 # 03 Y:2017 03 2017 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF $25,748 $19,769 Not Implemented
GT0908 # 06 Y:2017 06 2017 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $44,491 $135,000 Implemented
GT0908 # 05 Y:2017 05 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $24,538 $61,313 Implemented
GT0908 # 01 Y:2017 01 2017 TURN OFF EQUIPMENT WHEN NOT IN USE $5,412 $125 Implemented
OR0694 # 02 Y:2017 02 2017 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $78,503 $7,018 Not Implemented
OR0694 # 04 Y:2017 04 2017 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $29,962 $12,100 Not Implemented
BS0108 # 05 Y:2017 05 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,696 $1,050 Not Implemented
BS0108 # 03 Y:2017 03 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $104 $165 Not Implemented
BS0108 # 01 Y:2017 01 2017 OPTIMIZE PLANT POWER FACTOR $6,587 $25,166 Not Implemented
OR0694 # 06 Y:2017 06 2017 MINIMIZE WATER USAGE $8,079 $15,125 Not Implemented
OR0694 # 03 Y:2017 03 2017 INSTALL BACK-UP EQUIPMENT $219,130 $45,000 Not Implemented
OR0694 # 01 Y:2017 01 2017 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $190,250 $7,842 Not Implemented
BS0108 # 02 Y:2017 02 2017 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $3,658 $290 Not Implemented
OR0694 # 05 Y:2017 05 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,605 $10,606 Not Implemented
BS0108 # 06 Y:2017 06 2017 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $240 $270 Not Implemented
BS0108 # 04 Y:2017 04 2017 INSTALL OCCUPANCY SENSORS $443 $1,238 Not Implemented
AM0740 # 06 Y:2017 06 2017 USE SYNTHETIC LUBRICANT $1,465 $0 Not Implemented